Complex Schedule

Week of

 Dec 14th  2009

Ver 12/15/2009 pws

 

 

Schedule for 12/16, 2009

 

 Time and date

Action

Personnel

·        0400

·        Siemens MG set turn off, bearing removal

·        6 and 8 o’clock to XA (experimental access)

·        4 o’clock to RFNA

·        I lim key to MCR

·        PSG

·        MCR

·        MCR

·        MCR

·        0700

·        CA LOTO applied to AGS

·        CA Access to sector 6 for ps work

·        CA Access sector 12 for SC work

·        CAS

·        MCR

·        MCR

·        0800

·        Access sector 9 for ps work

·        MCR/HP

·        0900

·        Access to AGS via north conjunction gate

·        All RHIC access ends, I lim key to 1004b

·        MCR/CAS/HP

·        MCR

·        1100

·        Secure AGS, remove LOTO

·        MCR/CAS

·        1200

·        Restore beam in Booster

·        MSG/MCR

·        1200-2400

·        Tune injectors as necessary

·        MCR

·        ~2000

·        Sweep secure RHIC experimental areas

·        MCR/CAS

·        2400

·        Restore AGS

·        Continue with beam development in RHIC

·        MCR

·        AP

         

Note that only a limited number of jobs will be done during this period. Any requests must be submitted and reviewed.

To check the list of approved jobs see:

 

/AGS/Accel/Maintenance/Requests/  

 

 

Reminder- Accelerators are now operational. All work must be submitted, approved and scheduled

 

To submit go to JOBS

 

For a time table Ring Access See Ring Access

 

Ver Tuesday, December 15, 2009 pws