RHIC pp Run 2003

Setup by Haixin Huang, huanghai@bnl.gov, x5446.

Last updated: 




Rhic Polarized Proton Run 2003  Status

Tue Mar 25 12:00: RHIC is currently in scheduled maintenance period after  11 weeks of d/Au run. RHIC is scheduled back to polarized proton commissioning mode tonight around 9PM and starts the 5 weeks polarized proton commissioning.

Rhic Polarized Proton Run 2003 Planning

Start Up (2 weeks) (March 26- April 9)

Setup and Injection (3-5 days from Wednesday Mar 26,  target date: Mar 29-31)

RHIC Energy Ramping: pp (4-6 days, target date: Apr 2- 6)

RHIC Top-Energy and Collision Tuning: pp (4-5 days, target date: Apr 6-11)

 

Organization

List of Tasks

Progress Reports

Recipes


RHIC shift leaders schedule
polarized proton phone list

Setup Plan

RHIC dAu FY03 elog and pp elog

Recipes

C-AD Spin pages

Goal of the run in pdf

 

RHIC Status

 

 


AGS Polarized Proton  Commissioning

 

Organization

List of Tasks

Progress Reports

Recipes

AGS Shift leaders schedule
 polarized proton phone list

polarization scan, 03/13/2003

RHIC dAu FY03 elog and pp elog

 E880 polarimeter & target

C-AD Spin pages

 

 AGS progress

 

More recipes