(last updated on 02/14/07)
set up plan always in progress ... stay tuned!
| task |
goal |
who? |
time/ status |
| setup and check power
supplies |
check all power supplies,
controls, readbacks etc. |
George et al. Steve, Al |
|
| RF conditioning |
operating voltages for
all
cavities |
John Butler, Alex Zaltsman, et al. |
|
| Abort kicker thyratrons |
test abort system,
evaluate
kicker stability (misfires?) |
Jianlin Mi et al. |
|
| AGS extraction, AtR tuning |
prepare injection into
RHIC, tune AtR up to W-dump - depends on RS loto - automated emittance measurements |
Nick, Woody, operations |
| task |
goal |
who? |
time |
status |
| Synchro |
AGS to RHIC synchro, set
target
frequency |
RF group |
done |
|
| AGS extraction, AtR tuning |
prepare injection into
RHIC through X- and Y-arcs |
Nick Tsoupas, RHIC operations |
done |
|
| Blue initial injection, coasting beam |
when blue magnets are
ready (w
or w/o hysteresis) try to inject, check for obstacles, establish 1st turn and coasting beam - injection with kicker off (bo6-tv9 and yo5-tv9 to 1.3 mrad) - injection with kicker timing adjustment - minimize injection losses, goal: > 90% - improve/optimize beam lifetime, prepare for RF work |
all, RHIC operations, Wolfram |
2 evening & night shifts |
done |
| RF work |
capture establish optimal voltage |
RF group |
evening & night shifts 1/2 shift |
done |
| RHIC blue magnet setup |
check-out cold magnets,
train DX
magnets, establish hysteresis to gamma 107.4, confirm ramp and quench protection software, exercise ramps |
George et al. Steve, Al |
day shifts 5 days (parallel) |
done (some may need to be repeated after partial warm-up) |
| Instrumentation |
begin Instrumentation
setup (see
Start Up Mode) - rev tick needed, BPM timing (Rob, Todd) - tunemeter (Rob, Angelika) - others (BBQ, ...) |
Rob, Todd, ++ |
evening & night shifts 1 1/2 shifts |
done |
| Sextupole polarity check |
circulating (bunched)
beam at
injection (requires BBQ): - check old sextupole configuration - check magnet polarity |
Todd, Yun |
1/2 shift |
done? |
| RHIC yellow magnet setup, magnet ramps |
see blue magnet setup test ramps, hysteresis ramps |
George et al. Steve Al |
day shifts 5 days (parallel) |
-- pending -- |
| Non-linear chromaticity (could bump into next mode, depends on magnets) |
blue ring with beam at
store - check again that old configuration & correction works - check new scheme out with beam |
Yun, Nikolay, Steve, Todd |
at least 1 shift |
|
| ORM @injection |
- requires timed in BPMs - can be done with blue only before yellow is cold (good if we can't ramp yet) |
Todd |
1/2 shift |
|
| transverse injection
matching |
parallel or
semi-parasitic, - can be done with just blue only |
Todd |
1/2 shift |
|
| IPM channel calibration |
Roger |
1/2 shift |
||
| beam based alignment |
take data, analyze
offline, determine offsets |
Jennifer, Todd |
1/2 shift |
| task |
goal |
who? |
time |
status |
| yellow injection |
establish injection,
circulating beam, bunched beam, lifetime |
all |
1/2 shift |
|
| Instrumentation Setup - BPMs - Tunemeter (Artus) - Injection Damper - Schottky (LF & HF) - BBQ, BTF - IPM - WCM - ? |
Timing, polarity, offsets timing (tunes < 0.5) timing |
all: Todd Rob, Angelika Rob, Angelika Kevin B Pete C. et al. Roger C Roger L |
done for blue |
|
| Machine Tuning - orbit correction - bend trim/orbit radius - decoupling - chromaticity - optics measurements |
Vadim Yun Steve T. Mei, Todd |
done for blue |
||
| BBQ feedback development |
Pete C., Carl S., Al et al. |
6 shifts |
in progress |
|
| Ramp development intensity < 0.2 109/bunch, 6 bunches corrector settings from Run4 |
- try to use old
corrector settings for injection and early ramp (up to beta = 3m), then propagate |
all |
6 days |
|
| radial loops | ||||
| try BBQ tune & coupling feedback | Pete, Carl, Al, Yun | |||
| orbit corrections along the ramp | < 1 mm | Vadim |
||
| transition crossing | timing, chromaticity jump, octupoles? | Christoph | ||
| transition monitor | commission scope &
software - scope should deliver data for 100-200 revolutions around transition into SDDSVIEW (get help to write code for handling SDDSformat early) |
Mike B., Angelika, Roger L |
||
| decoupling along the ramp | - use IR skew settings
from previous run (run 6, pp) not Run 4 (IR6 triplet rolls were since corrected mechanically) |
Yun | ||
| chromaticity along the ramp | ~ 2-3 units, chromaticity jump | Steve T, Christoph | ||
| IR orbit separation, longitudinal sep. | - BPM offset in triplets?
need measurement (w. beam?) |
Vadim |
||
| exp. magnets | PHENIX & STAR switch
on at store, adjust ramp |
all |
||
| Store
development 6-56 bunches |
increase bunch intensity to > 1 109 establish collisions, DX BPM timing |
all Todd |
5 days (total) |
|
| Store optics |
orbit correction,
decoupling,
chromaticity Dispersion function measurement and correction IR nonlinear corrections Betatron tune scans: working point scans optics measurements (AC dipole) |
Vadim, Yun, Steve T all all Fulvia all Mei, Todd |
||
| collimation setup |
initial setup |
Angelika |
1/2 shift |
|
| gap cleaning setup |
initial setup |
Angelika |
1/2 shift |
|
| 10 Hz feedback |
evaluate, commission |
Christoph |
||
| store 2 store
reproducibility |
all |
|||
| rebucketing |
reduce vertex w. storage
cavities |
RF group |
| task |
goal |
who? |
time |
status |
| ramp development with
intense
beam |
define optimal operation
parameters, observe emittance - extra attention to bunch2bunch emittance - monitor emittance of last bunches in train carefully |
all |
7 days |
|
| pressure rise |
SY, Haixin .. |
|||
| higher number of bunches
ramp
development |
gradually increase beam
intensity, number of bunches reduce beam losses verify longitudinal separation |
all |
||
| collimation on the ramp? |
Angelika |
|||
| detector background |
optimize orbits, improve
collimator setup |
Angelika, all |
||
| optimize gap cleaning |
Angelika |
|||
| optimize beginning of
store |
Greg |