Au-Au Run 7  Machine Set Up Plan

(last updated on 02/14/07)
set up plan always in progress ... stay tuned!



Pre - Start Up  (before any ring is at operating temperatures)

 
task
goal
who?
time/
status
setup and check power supplies

check all power supplies, controls, readbacks etc.
George et al.
Steve, Al

RF conditioning
operating voltages for all cavities
John Butler,
Alex Zaltsman, et al.

Abort kicker thyratrons
test abort system, evaluate kicker stability (misfires?)
Jianlin Mi et al.

AGS extraction, AtR tuning
prepare injection into RHIC, tune AtR up to W-dump
- depends on RS loto
- automated emittance measurements
Nick, Woody, operations



    Cool-Down Mode (~10 days, only evening and night shifs, Feb. 19- Feb. 24, interrupted by cryo problems
    continue Mar 9)

task
goal
who?
time
status
Synchro
AGS to RHIC synchro, set target frequency
RF group

done
AGS extraction,
AtR tuning
prepare injection into RHIC
through X- and Y-arcs
Nick Tsoupas,
RHIC operations

done
Blue initial
injection,
coasting beam
when blue magnets are ready (w or w/o hysteresis) try to inject,
check for obstacles, establish 1st turn and coasting beam
- injection with kicker off (bo6-tv9 and yo5-tv9 to 1.3 mrad)
- injection with kicker timing adjustment
- minimize injection losses, goal: > 90%
- improve/optimize beam lifetime, prepare for RF work
all,
RHIC operations,
Wolfram
2 evening &
night shifts
done
RF work
capture
establish optimal voltage
RF group
evening &
night shifts
1/2 shift

done
RHIC blue magnet
setup
check-out cold magnets, train DX magnets, establish hysteresis to
gamma 107.4, confirm ramp and quench protection software,
exercise ramps
George et al.
Steve,
Al
day shifts
5 days
(parallel)
done (some may
 need to be
repeated after
partial warm-up)
Instrumentation
begin Instrumentation setup (see Start Up Mode)
- rev tick needed, BPM timing (Rob, Todd)
- tunemeter (Rob, Angelika)
- others (BBQ, ...)
Rob,
Todd,
++
evening &
night shifts
1 1/2 shifts
done
Sextupole polarity check
circulating (bunched) beam at injection (requires BBQ):
- check old sextupole configuration
- check magnet polarity
Todd, Yun
1/2 shift
done?
RHIC yellow magnet
setup, magnet ramps
see blue magnet setup
test ramps, hysteresis ramps
George et al.
Steve
Al
day shifts
5 days
(parallel)
-- pending --
Non-linear chromaticity
(could bump into next mode,
depends on magnets)
blue ring with beam at store
- check again that old configuration & correction works
- check new scheme out with beam
Yun, Nikolay, Steve, Todd
at least 1 shift

ORM @injection
- requires timed in BPMs
- can be done with blue only before yellow is cold
(good if we can't ramp yet)
Todd
1/2 shift

transverse injection matching
parallel or semi-parasitic,
- can be done with just blue only
Todd
1/2 shift

IPM channel calibration

Roger
1/2 shift

beam based alignment
take data, analyze offline, determine offsets
Jennifer, Todd
1/2 shift

  


Start Up Mode (10 days, 3 shifts per day, evtl. 2 shifts per day, nights for experiments, begins when both rings are cold,

Mar 15 - Mar 25)

    - once store development starts experimental magnets should be ON

task
goal
who?
time
status
yellow injection
establish injection, circulating beam, bunched beam, lifetime
all
1/2 shift

Instrumentation Setup
- BPMs
- Tunemeter (Artus)
- Injection Damper
- Schottky (LF & HF)
- BBQ, BTF
- IPM
- WCM
- ?

Timing, polarity, offsets
timing (tunes < 0.5)
timing
all:
Todd
Rob, Angelika
Rob, Angelika
Kevin B
Pete C. et al.
Roger C
Roger L



done for blue
Machine Tuning
- orbit correction
- bend trim/orbit radius
- decoupling
- chromaticity
- optics measurements


Vadim

Yun
Steve T.
Mei, Todd

done for blue
BBQ feedback development

Pete C., Carl S.,
Al et al.
6 shifts
in progress
Ramp development
intensity < 0.2 109/bunch, 6 bunches
corrector settings from Run4
- try to use old corrector settings for injection
and early ramp (up to beta = 3m), then propagate
all
6 days

radial loops



try BBQ tune & coupling feedback
Pete, Carl, Al, Yun

orbit corrections along the ramp < 1 mm Vadim


transition crossing timing, chromaticity jump, octupoles? Christoph

transition monitor commission scope & software
- scope should deliver data for 100-200 revolutions
around transition into SDDSVIEW (get help to write
code for handling SDDSformat early)
Mike B., Angelika,
Roger L


decoupling along the ramp - use IR skew settings from previous run (run 6, pp)
not Run 4 (IR6 triplet rolls were since corrected mechanically)
Yun 

chromaticity along the ramp ~ 2-3 units, chromaticity jump Steve T, Christoph

IR orbit separation, longitudinal sep. - BPM offset in triplets? need measurement (w. beam?)
Vadim


exp. magnets PHENIX & STAR switch on at store,
adjust ramp
all


Store development
6-56 bunches

increase bunch intensity to > 1 109
establish collisions, DX BPM timing
all

Todd
5 days
(total)

Store optics
orbit correction, decoupling, chromaticity
Dispersion function measurement and correction
IR nonlinear corrections
Betatron tune scans: working point scans
optics measurements (AC dipole)
Vadim, Yun, Steve T
all
all
Fulvia

all
Mei, Todd


collimation setup
initial setup
Angelika
1/2 shift

gap cleaning setup
initial setup
Angelika
1/2 shift

10 Hz feedback
evaluate, commission
Christoph


store 2 store reproducibility

all


rebucketing
reduce vertex w. storage cavities
RF group



    Ramp Up Mode (1 week, 1-2 shifts per day, Mar 25-Mar31 )

task
goal
who?
time
status
ramp development with intense beam
define optimal operation parameters, observe emittance
- extra attention to bunch2bunch emittance
- monitor emittance of last bunches in train carefully
all
7 days

pressure rise

SY, Haixin ..


higher number of bunches ramp development
gradually increase beam intensity, number of bunches
reduce beam losses
verify longitudinal separation

all


collimation on the ramp?

Angelika


detector background
optimize orbits, improve collimator setup
Angelika, all


optimize gap cleaning

Angelika


optimize beginning of store

Greg



    Physics Running (day shifts if needed, Mar 26 -> Jun 30)