(based on similar plans for previous RHIC Runs)
| Wednesday
Nov 15 |
9:00 am - 12:00 pm |
1:30 pm - 5:00 pm |
meeting 9:00
am in MCR |
| Thursday Nov 16 |
9:00 am - 12:00 pm
|
1:30 pm - 5:00 pm |
meeting 9:00 am in
MCR |
| Friday Nov 17 |
9:00 am - 12:00 pm
|
1:30 pm - 5:00 pm |
meeting 9:00 am in
MCR |
Please check if:
| System | commissioner |
comments |
time |
status |
changes |
| Elog |
Todd, Ila, Angelika |
available? any new
features? |
9:15-9:30 |
N |
|
| AtR |
Nick T., Woody ... |
setpoints for Au, AtR
managers, AtR orbit, BPMs, loss monitors, emittance measurements
(automatic measurements, records?) |
9:15-12:00 |
? |
|
| RHIC operations GPMs,
StartUp |
operations, Angelika, Greg |
ramp, magnets, beam
current, fill pattern, SpecMan, etc. |
9:15-10:30 |
? |
|
| Logger |
Roger L. |
test |
9:15-10:30 |
N |
|
| LogView |
Ted |
test |
9:30-10:30 |
Y |
|
| Permit Link |
Rob, operations |
check out |
10:00-11:00 |
N |
|
| Abort kickers |
Leif, ... |
check out |
10:00-11:00 |
N |
|
| Plotfill, FDAview |
Todd |
test |
10:30-12:00 |
Y |
|
| BLAM |
Jonathan, Greg, Leif |
test |
11:00-12:00 |
? |
|
| RHIC Injection |
Wolfram, ... |
event generation and
detection, software changes?, check out |
1:30-2:30 |
N |
|
| Sequencer |
Ted, Jen, Todd, Molly,
Nick K., ... |
new C++ version, test |
1:30-4:00 |
Y |
|
| tape |
Jen |
combined
test w. sequencer, mode switching for dAu |
1:30-4:00 |
Y |
|
| Configuration Control |
Greg, Angelika |
check status |
1:30-3:00 |
Y |
|
Day 2 (instrumentation)
| System |
commissioner |
comments |
time |
status |
changes |
| IPM |
Roger C, Steve T |
test application |
9:15-10:30 |
? |
|
| WCM |
Roger L |
test, new scopes, ethernet |
9:15-10:30 |
Y |
|
| RHIC vacuum, pressure
display |
Dick H, Haixin, Seth |
test (application) |
10:00-11:00 |
N |
|
| e- detectors |
SY, Angelika, ...? |
check out, test |
11:00-12:00 |
? |
|
| AC dipole |
Mei |
work test |
10:00-11:00 |
N |
|
| transition monitor
(button pickup) |
Mike Blasko, Angelika,
Roger L |
test application |
10:00-11:00 |
Y |
|
| BPMs |
Rob, Todd |
managers, timing |
10:30-12:00 |
Y? |
|
| Tune Meter (Artus) |
Rob, Angelika, Jonathan |
test new software |
9:15-10:00 |
Y |
|
| Injection Damper |
Rob, Angelika |
check out |
10:00-10:30 |
N |
|
| BBQ, feedback, transition
monitor, BTF |
Pete C, Al, Carl, ... |
test, check out |
9:15-12:00 |
Y |
|
| Schottky |
Kevin, ...? |
test |
1:30-2:30 |
? |
|
| RF, applications |
Tom H |
check out |
1:30-2:30 |
? |
|
| collimators |
Angelika, Wenge |
test, start from sequencer |
1:30-4:00 |
Y |
|
| gap cleaner |
Angelika, Wenge |
test, start from sequencer |
1:30-4:00 |
Y |
|
| Tune Display |
? |
test |
2:30-3:30 |
? |
|
| Loss Monitors & Thresholds |
Mei, Seth |
RHIC, AtR, injection data |
2:30-3:30 |
N |
|
| Jump Quads |
Christoph |
test |
1:30-2:30 |
N |
|
| 10 Hz Feedback |
Christoph,... |
status?, check out |
2:30-3:30 |
Y |
|
| polarimeter |
Haixin, Seth, ... |
test polarimeter hardware
and software in case of pp |
2:30-4:00 |
Y |
| System |
Commissioner |
comment |
time |
status |
changes |
| Ramping systems & online model |
Al, Steve, Nikolay, Todd |
WFG manager, online model
... OrbitCalc, online-offline interface ... |
9:30-12:00 |
Y |
|
| OrbitDisplay |
Vadim |
test |
9:15-10:30 |
? |
|
| LISA |
Ted, Angelika |
test new features |
11:00-12:00 |
Y |
|
| Orbit Correction |
Nikolay, Vadim |
test (new features?),
ramp correction ... |
1:30-3:00 |
Y |
|
| Skew Mod | Yun |
check out |
9:15-10:30 |
? |
|
| Ramp Editor |
Steve T, Todd, ... |
test |
1:30-3:00 |
Y |
|
| Rhic Chromaticity |
Steve T |
test |
3:00-4:00 |
? |
|
| DQmin |
Joanne |
test |
10:00-11:00 |
? |
|
| BERT |
Greg, Seth |
test |
1:30-2:30 |
N |
|
| RhicLumi |
Seth, Angelika |
test |
2:30-3:00 |
Y |
|
| Store Automation |
Greg, Angelika |
status? |
3:00-4:00 |
Y? |
|
| IR Bump |
Fulvia, Sev |
test |
10:00-11:00 |
N |
|
| sequencer |
Ted, Jen, Todd, Molly, Nick K., ... | revisit |
3:00-4:30 |
Y |
please contact Angelika (drees@bnl.gov or x2348) for more information or comments.