Old 2001 Scheduling Physicist News Bulletins

Angelika Drees, drees@bnl.gov, 344-4732, pager 4300 Last updated:




SEB progress May 25 - June 16:

Fri May 25: Beam is delivered to E931 as of 7:30 pm yesterday, May 23. We had no significant interruptions last night until this morning 8:30 when a vacuum pump failed in  the C-line switchyard. Since about 11:00 am we're on and off due to a C-line power supply failure. At this point we are working on it and should have beam back later this afternoon. This (Memorial Day!) weekend including next tuesday we have running for E949 and E931 scheduled. Next wednesday we plan another maintenance day (7:00-14:00) including the usual suspects (see below). If you need any access, please contact Ray Zaharatos.
Tue May 28: Last friday, after assorted power problems and the (partial?) power dip we came back on around 18:00. At 23:00 a power line failure for the C3-line caused the E931 He target to warm up. Cooling down after the repair took approximately 2.5 days and they started taking beam again  late monday evening.  Therefore their running time is extended until Jun 10, 8:00 am for compensation.  E949 took data all weekend. Although there were no other significant interruptions we had continuous problems with C-line magnet power supplies (CQ6/7, CP464), the AGS main magnetic field drifting and once with the vacuum valves in LESB III.  Beam was extracted from the AGS with 65-70 Tp. There is a maintenance day planned tomorrow (7:00 - 13:00).
Thu May 30: Beam was back at 16:00 after yesterdays maintenance. Startup was delayed because of a BTA quad failure. Intensities were close to 70 Tp until last night when sporadic problems with LINAC extraction occurred (probably after a power dip).  Intensity is stable again since 7:00 am and AGS efficiency was about 70%. There were no significant interruptions today.
Tue June 4: Since yesterday there were no significant interruptions. E949 and E931 are taking data. LESB II separator voltages were improved during the last conditioning period to +/- 265 kV and +\- 220 kV.  It was lowered today to +\- 180 kV on the latter one. We'll try to work it up on monday (no guarantee!). Sep. 1 in LESB III is stable at its reduced setpoint. The next maintenance is planned for Wed., Jun 05. --
The LESB-III #1 separator has what appears to be a busted vaccum window, and will require at least 1/2  a day to repair, according to Tom Russo. While we wait for his full assessment,  SNS tests are running in the LINAC.
Thu June 13: Summary of the past week: AGS was off for the LESB III separator 1 vacuum repair for 2 days, Jun 04 and Jun 05. There were no further significant interruptions for the remaining 4 days and the AGS delivered 70-75 Tp protons to E949 with ~ 8Tp to E931 until Jun 09, 24:00. The PRAD test on monday and the  bunch merging study for E951 on tuesday were both successful. Most parts of the program for the PRAD test, such as Multi-pulse extraction, two different intensities  and variable pulse spacing, worked.  During the bunch merging study single bunch intensities of up to 10 Tp could be achieved (where < 7 Tp were the record so far and the ultimate goal is 17 Tp). While the AGS was shut off after those studies the LINAC continued to run with polarized protons and for a fault study. After opening the HEBT line tomorrow, there will be one more SNS laser/wire study on sunday (see below). From sunday, Jun 16, 24:00, all CA-D machines including LINAC will be in scheduled shutdown and the work on the BAF begins.
 





SEB progress May 08 - May 24:

Thu May 09: Beam after the access yesterday was back by 12:15 :) with about 40-50 Tp. Full intensity (65 Tp) was back 2 hours later. We are running since then without significant interruptions :) for E949 and E958.
Fri May 10: Since yesterday morning the separator #1 in LESB III (E949) has problems with the positive plate. The voltage had to be reduced to a total of 250 kV (from 350 kV).  We inspected it and it looks like an internal problem. It cannot be fixed before the end of the program.  Since we turned beam back on last night it appears stable at it's reduced voltage and we continue the program with > 65 Tp for E949 and E958 (Crystal Ball).  This morning we lost a few hours due to a LINAC RFQ problem. However, the third week of the extension is now still questionable and not yet confirmed.The cryo group started purging the He-target for the E931 experiment and will start cooling on monday. The target will be ready by Friday next week, May 17.
Mon May 13: There were no significant problems over the weekend and we ran with > 90% efficiency and up to 70 Tp extracted intensity. Separator 1 is still limping along with +150 kV/-100 kV.
Tue May 14: SEB continues with up to 70 Tp and only minor interruptions (< 15 min.). Separators are at reduced voltages. The E931 target will be ready early morning Sat May 18. C target temperature is getting closer to the limit, we might have to lengthen the spill and reduce the particle momentum.
Thu May 16: Yesterdays access took 1.5 h longer than scheduled. Separators were conditioned, including LESB II with E931 set points. Sep 1 in LESB III turned out be a bit higher (300 kV vs. 250 kV). LINAC ran for SNS for some hours. However, it was not before 6:30 pm that we had beam back. A problem with the F5 extraction septum supply kept us of for most of the time :(.
Crystal Ball (E958) got an extension of 5 days until May 22 (see schedule below). E931 start up moves accordingly. E931 will run for 2 weeks, i.e. until Jun 05. This assumes a continuation of the E949 till Jun 07 (at least) and excludes proton radiography and bunch merging studies on the Jun 01/02 weekend.
Fri May 17: Last night we had problems with LESB II vacuum and Crystal Ball was off for almost 10 h. The problem was hard to diagnose. Thanks to Tom Russo and his crew and E949 who agreed to two accesses to this area we could fix the same night (thanks!). E949 lost about 2 1/2 hours because of it.  Another 2 hours were lost due to a LINAC  problem. This afternoon we were/are running for KOPIO (parasitically). This supposedly is the last time for them this run and they could do all tests they had on their list. Right now  we are extracting beam with up to 65 Tp and deliver to E949 and E958. To keep running is the plan for the weekend and early next week until wednesday morning when we scheduled another maintenance day.
Mon May 20: AGS was running with approx. 62 Tp without significant interruptions over the weekend for E949 and E958. We are planing a maintenance day on wednesday, May 22 for separator conditioning (etc.), switch-over from C6->C8 and F3 kicker repair. The later needs to be confirmed. If the kicker repair is on, we'll go off on midnight and allow cool down for about 8 h before the repair work begins. Startup with beam is then scheduled for early afternoon, 2:00 pm.
Tue May 22: Due to a vacuum/pump failure in LESB III the AGS went off around 6:00 am this morning. In order to work on this problem, several hours of cool down are necessary and an ALARA committee meets now to address it. Since we were off anyway, we changed gears and we'll do the maintenance items which were originally on the list for tomorrow (see below). An optimistic guess for beam is 6:00 pm today. There will be no other maintenance this week. Crystal Ball got additional time to compensate for the loss while avoiding the night for the switch-over to E931.  Therefore we'll start E931 on thursday, May 23.
Thu May 24: Beam is back since 6:00 pm on tuesday and had no further interruptions. As of this morning, the E958/Crystal Ball experiment is finished. The switch-over to E931 is almost done and they are setting up their detectors. Separators in LESB II were conditioned today and are waiting for the finishing touch with magnets on (needs to be done by experiment). There were 2 hours down time today due to a water leak in LESB II.
 





SEB progress Apr 23-May 07:

Thu Apr. 25: Separator conditioning was done yesterday, Apr. 24. AGS was open from 9:00-11:30, beam was back by 12:30. While the luminescence monitor installation was finished in the AGS, the Westinghouse was inspected and LINAC ran for SNS laser/wire monitor for 3 h. When coming back from the access period a not yet understood booster RF timing problem caused a slightly worse transmission efficiency. However, intensities are in the order of 60 Tp anyway. Last night we had smooth operation with both Experiments, E949 and E913/927 taking beam. E913/927 did shut off around 6:30 am until further notice to analyze their data and work on their detector. They will come back on within a few days. This morning, Apr. 25, we went off around 9:00 am due to a  Westinghouse controls problem. At this point we are still off and trouble shooting the problem.
Fri Apr. 26: AGS was running well over night and today with intensities above 60 Tp . This afternoon shortly after 16:00 we got a problem with the extraction bump power supply such that about 25 Tp were lost at transition each cycle. The power supply appears to be shorted and we are currently working on it. Estimate for beam is around 7:00 pm tonight. LESB III & II separators are still operated at reduced voltages and E949 is taking data. E913/927 continues working on their DAQ and the drift chamber electronics, most likely over the weekend. They might resume data taking early next week.
Mon Apr. 29: AGS ran without significant interruptions over the weekend.  Intensities were around 65 Tp. E949 took data and by saturday early afternoon Crystal Ball resumed data taking as well. They will - based on current funding - run for one more week. Intensities delivered to C3 target are around 8 Tp.  Wednesday we'll have another 4-5 h separator conditioning period.
Wed May 1: Yesterday afternoon we had problems with AGS RF stations and intensities were poor or limited to < 65 Tp respectively. The RF crew worked on this and 2 other stations during this mornings maintenance. During the evening we went off because of a LINAC  failure and experimental access (E913). This morning at 3:15 we went off when a BtA magnet  and booster RF failed. There was no more beam before we started the maintenance period.  Separator conditioning and Westinghouse inspection was done together with AGS RF work and BtA magnet work, which all together took a bit longer than anticipated. LINAC ran for SNS. Beam was back shortly after 1:30 pm. Since then MCR is struggling to restore SEB due to ongoing problems with BtA and AGS extraction. LESB II is off since Crystal Ball is using a lead target instead.
Fri May 3: From Wednesday night 20:00 we were back in business and were delivering 60-65 Tp on C-target. We had one interruption from 7:00-9:00 am this morning when we had to compensate for acceleration losses in the AGS. We are delivering beam right now, intensity is ~65 Tp. The plan for the weekend is running E949 and E927. Both experiments are taking data,  LESB II is still off and replaced by a lead degrader. It is planned to turn the separators back on some time tomorrow afternoon. In addition, I have good news today :). The run for the Crystal Ball experiment, namely E958, got extended by DOE for 1.5 weeks and will now end together with E949, on May 17 (current funding)!
Tue May 07: We had smooth running over the weekend, no significant interruptions. Extracted intensity was around 65 Tp with about 8 Tp on C3 target. E927 ended Monday, 24:00 and E958 started Tuesday, 00:00. Both experiments are taking data, E949 had 141 (168) hours with beam past week! Tomorrow morning we'll have  separator conditioning and Westinghouse maintenance combined with an AGS access (see below).





SEB progress Apr 03-Apr 23:

Tue Apr 09: Last week we had smooth SEB running with intensities around 70 Tp. The program was paused Sat, Apr 6, 8:00 am, to switch to Si beams for the NASA run. The switch over to 600 MeV Si beam was completed by midnight Apr 8. Beam is delivered to the A3 line since 8:30 am Apr 09. Biology run with samples started not before 5:00 pm this afternoon.
Wed Apr 10: The NASA run is progressing smoothly. 600 MeV Si beam was delivered without interruptions to the A3 cave all night and this morning. We are still running 600 MeV Si beam and will do so until tomorrow morning when we switch to 1 GeV Si beams.
Mon Apr 15: It took about 5 h to switch from 600 MeV Si to 1.1 GeV Si Thursday morning. Friday we switched to 1 GeV Fe beam and that's what we run since then. Saturday we had a 12 h interruption due to a TtB vacuum problem. The accumulated delays are about 48 h or 2 days. The anticipated end of the NASA program  is therefore some time Wednesday afternoon.
The separator conditioning didn't make as much progress as we were hoping for. Over the weekend, the negative plate could be brought up to 120 kV so far but has a high sparking rate.
Tue Apr 16: NASA accumulated another 8 h of delay over night until this morning when we went off because of a water flow problem in an AGS magnet power supply. This added 3 more hours. Therefore the anticipated end of the NASA program will be some time tomorrow afternoon (moved from 5:00 am). Exact timing might slide! Please check updated schedule below.
Separator conditioning/feedthru replacement didn't get us to a higher working point.  The highest voltage reached was 140 kV but unstable. For the upcoming weeks only asymmetric setpoints at +300 kV and -100 kV are realistic. Though the cause is yet unknown it might be a stand-off failure again.
Fri Apr. 19: NASA was finished 10:00 am Wednesday, Apr. 17.  LINAC ran for SNS laser/wire for about 8 h during the day. The test was only partially successful since DAQ problems could not be resolved and some more LINAC time is needed in the upcoming weeks. Booster access started am and AGS access early afternoon. The Fe20+ test in the booster was done by 23:00 the same day and did well: high charge state Fe beam got circualated and was accelerated successfully :). Thursday was spent on testing Westinghouse and setup for SEB. After some C-line lock and interlock problems during thursday evening hours, we're back to SEB running mode since 00:00 today, Apr. 19.  Separator #1 is set to +250 kV and -100 kV and  could - so far - not be improved further. However, weekly conditioning of about 4 h will be on the schedule for the next 4 weeks. Westinghouse was operated with a reduced duty cycle (6 s instead of 5.4 s) due to the high outside temperatures. This will be set back today, after an AGS access to fix a gap short problem in the KL cavity. The current estimate for beam is 17:30.
Mon Apr. 22: SEB program was running all weekend with some interruptions in the C6 beam line.  The LESB II separators were not stable with the required magnetic field and their voltage had to be reduced and new magnet settings needed to be found. Sunday we had a problem with the remote control of the C6 collimators which is fixed by now. However, by Saturday around noon the extracted intensity from the AGS was above 60 Tp :)  and is now peaking at almost 70 Tp again. E949 is taking data with a reduced kaon/pion rate due to the reduced separator voltage. E913 took some calibration/setup data and is currently working on their drift chamber electronics.
Tue Apr. 23: Today we had pretty smooth and stable operation with approx. 65 Tp extracted intensity and 8 Tp on the C3 target. LESB II separators are running at a reduced voltage and under hard vacuum while Crystal Ball is running with 700 MeV particles. LESB III sep. 1 is still operated at 350 kV . Both experiments are taking beam.
 
 



SEB progress Mar 29 - Apr 02 :

Fri Mar 22: This week the extracted intensity went up from about 55 Tp to 62 Tp. We are currently about 58 Tp with about 8 Tp on C3 target. Tuesday we did separator conditioning, Westinghouse maintenance and AGS RF repair. During that time the BLIP vacuum leak could be fixed and BLIP is running again since Wednesday this week. Quad pumping and phase feedforward was implemented in the booster RF later on Tuesday and is ON since then. There was no usefull beam before 22:30. Optimization is still in progress but beyond the point to be disruptive. Wednesday early morning E949 fixed their DAQ problem. Trigger rejection and deadtime were improved but is still in progress. Since Wednesay afternoon the AGS transverse damper is being used. Thursday we had the first successful (parasitic!) test beam down to the d-line for the K0PI0 experiment. Today we encountered a problem with dipoles in the d-line and we are still working on it. Therefore, K0PI0 test beam is postponed to Monday next week.  E931 had a problem with their liquid He-target for some time friday afternoon which is fixed now. For now both experiments are *happily* taking data. The plan for the weekend is physics running.
Tue Apr 02 0900: Sat Mar 30 we suffered lost time due to a serious power dip in the early morning, and only recovered beam operations late in the evening. Early Sun Mar 31 a vacuum problem developed in the J5 section of the AGS that degraded beam intensity to 50 Tp, then precluded beam operation altogether. High levels of radiation in that area (presumably due to vacuum problems and scraping beam) delayed repair until Mon Apr 1. A new seal was installed at J6 updstream and vacuum was restored at 1900, and late Mon Apr 1 AGS operations returned to 60+ Tp levels. We are currently running at 65+ Tp. :)
 
 


SEB progress Mar 03 - Mar 18 :

Mon Mar 04:The separator progress is promising. HV was turned up to 115 kV today and the separator continues to behave reasonably well. Tom Russo is going on with conditioning throughout the week. Therefore BAF shielding should be back in place tomorrow afternoon. By Wednesday morning both, booster and AGS, should be secured for beam. There will be no beam on the C-target before Friday. Wednesday will be spent on reviving booster & AGS equipment and Thursday on setup with some low intensity beam (see schedule below). LINAC will start delivering protons to BLIP on Tuesday, Mar 05. MCR shifts will start tomorrow, Mar 05.
Fri Mar 08: Separator progress is good (the plates are currently at +/- 250 kV) , although nominal gap voltage is not yet reached. Conditioning to final +/- 300 kV will still go on for a few more days while we start tuning beam for high intensity in the AGS and have full beam on the C-target ("full" means as much as we can at the time). Separator conditioning should not interrupt the program any more (cross fingers!!) but for the time being the beam is not yet fully separated.
Mon Mar 11: The AGS was quickly recovered from the shutdown state of the past weeks and extracted beam intensity approached 50TP per pulse by Sunday :). Failure time was due to a power dip from inclement weather Sunday morning. BLIP was off from sunday morning because of a vacuum leak. Separator 1 in LESB III was at +/- 500 kV over the weekend and will remain so for a few more days while voltage is increased in small steps only. Today was spent on asymmetrical conditioning of both, LESB III and II separators (after an increase of the sparking rate within the past 24 hours in sep. 1). No beam was delivered to E949 and E931 during this process. Vacuum was investigating the vacuum leak in the BLIP line and found a leaking bellow.
Wed Mar 13: AGS extracts intensities around 50 Tp while delivering 7 Tp down to the C' target :). Besides some minor problems with the AGS VHF and a VME controls problem things are going well. We continue working on increasing the intensities. KOPIO test beam shifts need to be re-evaluated. So far BLIP is off because of the vacuum problem, repair is only possible in case of some other maior hardware failure. E931 still takes data with their Cu-target, the He target will be moved into place tomorrow.
Thu Mar 14: Last night (Wed/Thu) AGS extracted beam intensity went up to almost 60 Tp at which point the C-target temperature limit was reached. This morning the AGS MMPS cycle was changed to 2.4 second flattop inside of a 5.4 second rep-period.  This improvement will take the duty factor up from 34 % to 40 % and will allow the intensity to go up to 65-70  TP on C-target (in 2.2 seconds) before hitting the temperature limit (which was also increased).  Most parts of the afternoon were spent on fixing a problem with the gap shorts in the IJ cavity and we were off from 13:00-17:00. Separators are still running fine (at +/- 250 kV) and spark rate is low.
Fri Mar 15: Extracated beam intensities with the extended spill length are pretty much the same or slightly higher (avg.: 56-57 Tp) as they were before (avg.: 54-55 Tp). MCR continues working on improving intensities. BLIP is pending the leak repair. So far separators are still doing well. Since Tom Russo anticipates to run the  separator HV above +/- 250 kV next week, a later than monday conditioning period is desirable (to get thru the following weekend). Therefore the conditioning shift is moved from monday to wednesday next week.
Mon Mar 18: Extracted beam intensity over the weekend and today was around 55 Tp with a 5.4 s Westinghouse cycle (2.2 s flattop). We check out 2 more cycles tomorrow (while separator conditioning is going on).
 
 


SEB progress Feb. 15 - Mar 01:

Fri Feb. 15: The separator vacuum improved a bit faster than expected. Right now the HV sits at +/- 50 kV (which is *nothing* compared to the final value). Tom Russo is prepared to get in tomorrow and sunday to work on conditioning over the weekend. By sunday night we'll know more. LIPA work on the substations will be finished by sunday morning 9:00 am, then booster MMPS will be ready for turn on. We'll probably start sunday during the day to bring booster/AGS components back to life.
Tue Feb. 19: Forget all I said so far.  The feedthru's are fine but the separator doesn't work and needs to be pulled out. Shielding was removed over the weekend Feb. 17/18 (President's day) and the separator is ready to be moved. Depending on the result of an additional survey (which dictates when we can start working on the separator). The delay is estimated to be approximately another 3 weeks (preliminary) . Better plans can only be made once the separator was opened and we know how to fix it. The AGS complex will be shut down for this time.
Wed Feb. 20: A standoff on the negative plate in LE3 has tracked and fractured inside the separator. It was very difficult to see even with the end flange off. Right now the separator is being moved to 919b. Tomorrow, once the RWP for the actual repair work is filed, work on the separator can begin. All standoffs have to be investigated before we decide to replace just one or all of them. Spare standoffs are available. At this point we anticipate about 1 1/2 weeks for the repair work.
Tue Feb. 26: Tom Russo and his crew are ahead of the schedule :) (estimating first beam for Mar 10): the separator is repaired - as far as they can tell - and back in 912 on top of the shielding. A first vacuum test is done tonight. If the tank holds the vacuum, it will be brought back into the pit tomorrow where it will be re-assembled and re-installed. If everything goes well we could start conditioning with HV as early as monday 03/04. There is no guarantee though that it will hold +/- 300 kV. Therefore there will be no beam on the C-target before it is shown to hold the design voltage.
Fri Mar 01: Tom Russo, Dan Lehn and their crew continue to work hard. The complete system - pipes and separator tank - is now vacuum tight. The roof shielding work started around noon today and should be finished by this evening. Heat was turned on in the separator over night. Vacuum still looks reasonably good. Tomorrow the HV cables will be routed and connected. Sunday we'll spent on (perhaps) low HV and heat conditioning while from monday on we'll continue with HV conditioning. First beam down the c-line is anticipated for Friday next week (so far). By Tuesday night we should know whether the repaired separator is doing better than before. Shielding in the booster stub tunnel has to be in place by the end of Tuesday next week. Wednesday we'll start to revive the machines and Thursday I hope we'll have some low intensity in booster and AGS to begin setup with beam.
 



SEB progress Feb 01-Feb 14:

During the past week, AGS extracted beam intensity had been increased up to 30 Tp. Thursday, Jan 31, LESB III separator #1 failed.  The separator feed-thru is going to be repaired. Therefore there will be no beam in the AGS today, Feb. 01. At the  same time we'll work on LtB bending magnet water flows (which failed last night) and check AGS for ground faults. From sometime tonight on "unseparated" beam can be delivered to E949 until separator is heated and conditioned. The conditioning process takes a few days.
We had semi-separated beam over the weekend and monday once the feed-thru's were replaced . Intensity was around 25 Tp. The VHF station which failed over the weekend was repaired today, monday, around 16:00. We got up to almost 50 Tp while still trying to condition sep#1 by thursday afternoon.
Thursday afternoon we decided to give up on conditioning separator #1 which would not get beyond 150 kV at which E949 cannot take data efficiently. Booster/AGS was turned off to allow cool down over night. Friday morning we started investigating the separator problem. By now, friday afternoon, it looks like most definitive that we have to get the separator to a shop and take it apart. This implies a down time of 2 weeks followed by one more week of conditioning with beam. During that time, LINAC will run at reduced energy of 139 MeV until Feb. 19. The tested newly assembled feedthrough did well in the test tank today, wednesday 02/13 :).  Linac mod 6 failed and will be off for at least 1 day to repair. Thursday: Both feedthru's did well in the test tank and are installed in the separator. HVoltage transmission system is
complete, temperature increased to about 70%, pressure is around some 10^-5 (wanted: < 210^-6). LINAC mod 6 is being worked on, we expect beam in the LINAC by tomorrow evening. Separator commissioning will start on saturday morning. Preferred feeder switch back will happen first thing monday morning. LINAC mod 6 still has some vacuum problems. We expect to be ready for beam tomorrow morning 9:00 am.


Update:


RHIC today: we did it!! At around 15:00 we had finally - after some struggle earlier with beam permits and snakes - 0.5 Tp beams with the ultimate lifetime in the machine, unsqueezed to beta*=10m at IR2, scraped to an emittance of 5-7 pi mm mrad and with a polarization of above 25% per ring !! The Roman Pots are inserted since 16:30 and right now the PP2PP experiment is taking data with this store and will hopefully continue doing so until 6:00 am tomorrow morning when we end this EXTREMELY SUCCESSFUL RHIC run. (well, I know, we didn't get *everything* done, but after all, we achieved quite something). I'm proud I could be part of it.

Planed Activities other than production:   (:  PARTY!   :)
                                             Join us next tuesday, Jan 29, at 4:00 pm in the 911 lobby
 

Activities past week:

date         time          activity
------------------------------------------------------------------------------------------
Wed Jan 16  6:00-14:00   beam studies - done
------------------------------------------------------------------------------------------
Fri Jan 18     1h  CONTROLLED access: install PHENIX photon converter, other areas
                         - pending store dump between 8:00 and 12:00 - done (+1h)
-------------------------------------------------------------------------------------------
Sat Jan 19     4h        PP2PP 3m beta* test run - pending store dump, ~ 12:00 am - done
-------------------------------------------------------------------------------------------
Sun Jan 20     4h        polarimeter calibration run - pending store dump, morning - done (+2h)
-------------------------------------------------------------------------------------------
Mon Jan 21     2h  CONTROLLED access:take out PHENIX photon converter
                         access to IR8, IP4, IR12, PP2PP (?)
                         - after first store dump in the afternoon - done (+1h)
------------------------------------------------------------------------------------------
Tue Jan 22     4h        beam studies: cancelled, instead: deceleration ramps 11:00-19:00 (done)
------------------------------------------------------------------------------------------
Jan 23                   production - done
------------------------------------------------------------------------------------------
Thu Jan 24  00:00-24:00  10m beta* low emittance/intensity run for PP2PP - done (+6h ?)
------------------------------------------------------------------------------------------
 

RHIC summary of the last 2 weeks:The weekend Jan 5&6:  was productive, we did more tune feedback studies (3 more successful ramps in blue), 200 MHz commissioning, injection tuning and polarimeter timing. As a result the beam intensity could be increased significantly and we had some good production stores during which we reached this years luminosity goal of  1.0-1.5 1030 cm-2 s-1 :)!  Monday Jan 7 we tried a first down ramp (beam lasted < 5 s) and worked on polarization in RHIC at the expense of  intensity resulting in lower intensity stores last night. Tuesday Jan 8 was spent on more 200 MHz commissioning and ramp tuning with one ramp where tune feedback worked in both rings - but beam got lost a second before flattop. 200 MHz will not be used  for the rest of the run. Wednesday Jan 9 morning a RHIC access was granted during which the STAR magnet polarity was switched. It will be kept off during ramps for the rest of the run.  Wed afternoon we had a booster vacuum problem. Once this was fixed we worked on ramping efficiencies and beam intensities. Ramp tuning later in the afternoon got us to above 3 Tp protons per ring for the last 2 stores (both pretty long). Luminosity was above 1 10^30 cm^-2 s^1 for most part of the stores :). The yellow polarimeter switched to another target this afternoon. 200 MHz cavities are not used. Thursday we had stores until 13:00 and tried injection steering for PHOBOS and orbit corrections in the afternoon. The stores after this had lots of backgrounds, some had to be dumped because of to high background in PHOBOS which seemed to be related to polarization measurements in blue at injection. Polarization measurements were then skipped. While having a problem with the booster extraction we had controlled accesses friday morning in various areas (IR12, IR2, IR6). They were smooth, we didn't loose any sweeps and everybody was out  before the booster could be fixed. Around 16:00 we started working with beam in RHIC at injection and will have production stores hopefully soon.
Saturday and Sunday we had beam stored and cogged for about 35 h (out of 48)!  Luminosity was typically around or above 1*10^30 cm^-2 s^-1 :).Various injector problems could hide behind RHIC stores. Polarization in RHIC was mostly around 20% at the beginning of a store but  dropping towards the end. Yellow intensity was up to 4 Tp, Blue typically below Yellow but above 3 Tp. While Yellow lifetime was stable, blue lifetime was dropping throughout most stores.
Monday morning, chromaticity was adjusted at flattop in Blue to help the lifetime. We tried 2 downramps, one w/o tune feedback (beam lasted 15 s), one with (beam lasted almost all the way down!). Operator error (not beam losses) caused a QLI. At this point we are filled and ready to ramp again. The plan for today and tomorrow is as much production running as possible. Tuesdaywe had stores over night with quite good (~ 20%) polarization in both rings. In the morning we were off for some time due to a FEC failure in a power supply crate.
In the afternoon we lost one store (with 23/26 % pol.!) while ramping the PHOBOS magnet (probably related to the polarity switch). We had one more bad ramps before we had stored beam again. During the night a vernier scan and a 20 minute scraping test was done.
Wednesday we had 2 stores over night until 6:00 am when beam study time started. Around 15:00 we had the first ramp. The store was lost after about 25 minutes due to a snake quench :(. Recovery time is about 1 h. Due to another QLI and RF cavity trips there was no more store before midnight. Thursday started with a very long store from 1:00 am to about 10:30 am this morning. Polarization at the end was above 10 % in both rings. Intensities started around 4 Tp for both rings, blue dropped to around 3-2.5 Tp and settled there while yellow (!) dropped to about 1.6 Tp at the end. Store ended with a spontaneous QLI, not related to any activity. During the afternoon/early evening some hours were spent to work on the PHOBOS magnet compensation. LINAC and source problems kept us of for some time too.
Friday started with a long store which was used at the end to finish the PHOBOS magnet compensation and to try another deceleration ramp which failed. The following  experimental access was extended due to problems with the PHENIX DAQ. A BtA magnet failure kept us off more most parts of the afternoon and we tried another deceleration with only 1 beam in the machine (blue). Saturday we had multiple stores over night. Around 13:30, just before the PP2PP run, we tried another deceleration (beam survived for about 60 s without significant losses before it got lost over the next 30 s). The PP2PP run with 6x6 was done without problems, beam was scraped at flattop to 1.2 10^11 total protons per ring. The plan for tonight until tomorrow morning, when the pol. calibration run starts, is production. Production continues tomorrow afternoon until monday. Sunday morning a 6h polarimeter calibration run was done. We had more physics stores thru the  rest of the day. During the night 2 more vernier scans were done followed by a background study for the PHENIX MuID detector. The spin pattern was changed on friday, now including 0 pol. bunches. However, the source control wasn't up to speed yet and a 0-bit was not yet implemented. This happened today after the calibration run. We'll continue with production stores until tomorrow early afternoon, when we'll have a 2 h exp. access. There will be more attempts to decelerate at the end of stores.
Monday Jan 21 we had stores over night and an experimental access from 14:30-17:30. One more deceleration attempt failed. From 22:00-1:00 we had a problem with the polarized source. Tuesday Jan 22: After the power supply was swapped in the polarized source we had one more store from 3:00-11:00 which was ended by a spontaneous QLI. The time from 11:00-19:00 will be spent on deceleration commissioning. Deceleration did not succeed. We should spent the night and tomorrow on production runs. Wednesday Jan 23: Deceleration study ended without success (although some progress). The night we had 2 more production stores (using collimators for halo scraping) until 5:30 when we got problems with a QLI PLC. That kept us off until 11:00. Since 11:20 we have another production store.
 
 
 
 

Westinghouse:   No more maintenance until the end of the pp run.
 


    Hoping for 40 Tp total, D-line should get 50%, i.e. 20 Tp, C target about 20 with C'
    target up to 5-6 Tp.

Current Access/Beam Schedule

The Plan for physics/MD: This is what happened (besides physics):
Date  Time  Notes  Time  Notes 
Tue Oct  9 00:01-24:00  RHIC physics, SEB 21.5 GeV/c running 10:30-11:30
11:30-21:00 
access (STAR tour)
AGS extraction bump problems
Wed Oct 10 00:01-4:00
8:00-24:00
RHIC physics, SEB 21.5 GeV/c running,
Exp. & RHIC & AGS maintenance period
2:00-5:30 problems with RHIC ramp
Thu Oct  11 00:01-24:00  RHIC maintenance 
AGS setup for higher intensities, SEB 
-   LTB problem 
Fri Oct 12 00:00-8:00
15:30-24:00
sweeping RHIC, getting ready for beam
RHIC physics, SEB
00:00-3:00
3:00-10:00
10:00-15:30
16:00-24:00
sweeping RHIC 
BTA transfer problems
setup with beam 
cryo problem
Sat Oct 13 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running  all day  problems with ramps, blow-up
Sun Oct 14 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running -   -
Mon Oct 15 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running    -
Tue Oct 16 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running 9:00-13:00
13:30-15:00
cryo problems
cryo problems

RHIC, Fri Oct 12, 2001 16:00:
Sweeping was done about 3:00 am this morning and followed by problems in the BTA transfer line. RHIC setup with beams at injection started around 10:00 am this morning. Right now we have a production fill with 55x55 bunches and use it for IR steering.

Fri Oct. 12, AGS extraction intensity:
SEB was running yesterday until about 2:30 am this morning to prepare for RHIC filling. D and C line SECs were calibrated but new calibration is not yet active. The numbers from this night are:

  • total: up to 34 Tp, no chipmunk limit at this point, room for more (slow) improvements but needs some work
  • D-line: 20.5 Tp, using the new calibration
  • C-target: 13 Tp, using the new calibration
  • C'-target: 7 Tp, using new calibration

  • Hoping for 40 Tp total, D-line should get 50%, i.e. 20 Tp, C target about 20 with C' target up to 5-6 Tp

    Current Access/Beam Schedule

    The Plan for physics/MD: This is what happened (besides physics):
    Date  Time  Notes  Time  Notes 
    Tue Oct  9 00:01-24:00  RHIC physics, SEB 21.5 GeV/c running 10:30-11:30
    11:30-21:00 
    access (STAR tour)
    AGS extraction bump problems
    Wed Oct 10 00:01-4:00
    8:00-24:00
    RHIC physics, SEB 21.5 GeV/c running,
    Exp. & RHIC & AGS maintenance period
    2:00-5:30 problems with RHIC ramp
    Thu Oct  11 00:01-24:00  RHIC maintenance 
    AGS setup for higher intensities, SEB 
    -   -
    Fri Oct 12 00:00-8:00
    15:30-24:00
    sweeping RHIC, getting ready for beam
    RHIC physics, SEB
    00:00-3:00
    3:00-10:00
    10:00-15:30
    sweeping RHIC 
    BTA transfer problems
    setup with beam 
    Sat Oct 13 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running  -   -
    Sun Oct 14 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running -   -
    Mon Oct 15 00:01-8:00
    ?-24:00
    morning
    RHIC physics, SEB 21.5 GeV/c running

    3-4 hours work on PLL tune feedback

      -
    Tue Oct 16 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running -

  • beta-squeeze ramps to 1m at PHENIX and BRAHMS: preparation not yet finished, probably some time during the weekend.
  • Data taking for PLL based tune feedback (3-4 h per ring @ injection): first 4 hours of Oct. 17 beam study time.
  • Beam studies: 12 h on Oct. 17, 6 am - 6 pm.
  • Landau damping RF cavitiy: quasi parasitic studies, eventually one dedicated 6x6 ramp.

  •  

     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     

    At this point there is no RHIC experiment maintenance scheduled. Ring Access is requested (but not yet scheduled) for aprox. 2 hours of work on the AC dipole (IP4) and the beam beam counters in IP12.


    Current Access/Beam Schedule

    The Plan for physics/MD: This is what happened (besides physics):
    Date  Time  Notes  Time Notes 
    Tue Oct  9 00:01-24:00  RHIC physics, SEB 21.5 GeV/c running 10:30-11:30
    11:30-21:00 
    access (STAR tour)
    AGS extraction bump problems
    Wed Oct 10 00:01-4:00
    8:00-24:00
    RHIC physics, SEB 21.5 GeV/c running,
    Exp. & RHIC & AGS maintenance period
    2:00-5:30 problems with RHIC ramp
    Thu Oct  11 00:01-24:00  RHIC maintenance 
    AGS setup for higher intensities, SEB 
    -   LTB problem 
    Fri Oct 12 00:00-8:00
    15:30-24:00
    sweeping RHIC, getting ready for beam
    RHIC physics, SEB
    00:00-3:00
    3:00-10:00
    10:00-15:30
    16:00-24:00
    sweeping RHIC 
    BTA transfer problems
    setup with beam 
    cryo problem
    Sat Oct 13 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running  all day  problems with ramps, blow-up
    Sun Oct 14 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running -   -
    Mon Oct 15 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running    -
    Tue Oct 16 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running 9:00-13:00
    13:30-15:00
    cryo problems
    cryo problems

    Current Access/Beam Schedule

    The Plan for physics/MD: This is what happened (besides physics):
    Date  Time  Notes  Time  Notes 
    Wed Oct 3 00:01-6:00, 
    14:00-24:00 
    RHIC physics, SEB 24/21.5 GeV/c running,
    8 h machine development 
    00:01-05:00
    6:00-14:00 
    controls problems 
    RHIC beam studies/development
    Thu Oct  4 00:01-24:00  RHIC physics, SEB running,
    some end of store work 
    10:00-11:30

    12:00 -2:00
    4:30-6:00 

    end of store work: crossing angle at 
    IP 10, rebucketing, 120 bunches
    3 beta*=2m squeeze ramps
    lead flow problem at 10/11 o'clock
    Fri Oct 5 00:01-24:00  RHIC physics, SEB 21.5 GeV/c running  17:00-18:00  3 more beta-squeeze test ramps
    Sat Oct 6 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running   8:00-23:00 work on beta squeeze ramps
    Sun Oct 7 00:01-24:00 RHIC physics, SEB 21.5 GeV/c running 8:00-15:00 IR steering for beta*=2m, 
    orbit corrections at storage
    Mon Oct 8 00:01-24:00  RHIC physics, SEB 21.5 GeV/c running,
    some hours of beta squeeze work
    12:30-16:00  improvement of beam liftetime,
    exp. access / QLI (power dip) 
    Tue Oct 9

    RHIC, Sun Oct 7 2001 12:30:
    We have a beta*=2m store with 55 bunches going right now. We work on orbit corrections, some decoupling followed by IR steering (none of the experiments does have collisions at this point). Once we get them steered we'll dump this store, fill again and try to go to production with beta*=2m and 55 bunches. 

    Sun Oct 7, AGS extraction intensity:
         total: 26-27 Tp, limited by NM032 chipmunk (tgt. bld. N catwalk)
         D-line: 18 Tp, limited by NM024 chipmunk (top d-line shielding)
         C-line: 5 Tp
         C3-line: 2 Tp
    D-line should have > 17 Tp and SEB C3-line should get 4 Tp, C-line accordingly less.

    Dedicated beam time requests coming up:

    • 120 bunch fill pattern work: dedicated RHIC fills/ramps on short notice
    • AGS-RHIC synchro: done friday Oct. 5
    • beta-squeeze ramps: basically all weekend, potentially (pending success) on monday or tuesday next week
    • data taking for PLL based tune feedback (3-4 h per ring @ injection): depending on the status of the machine we are trying one ring on monday.
    • beam studies: Not this week.


    The next RHIC experiment maintenance is scheduled to start Wed Oct. 10, 4:00 am (to allow 4 h of AGS cool down) - Thu Oct. 11. We're heading for sweeping RHIC late afternoon/evening Thursday. AGS should run during Thursday.


    Mon Sep 24 2001 21:15: We are back to RHIC operations and SEB tuning after an overnight RHIC store and a day of several unsuccessful RHIC ramps. RHIC ramps were known to be failing due to yellow radius excursions, though RF experts are investigating the root cause. The day Mon Sep 24 was spent in PHENIX photon converter access, RHIC ramp restoration, abort and injection kicker studies, beta-squeeze, and PLL testing for RHIC. RHIC 200 MHz storage RF is now routinely on during RHIC stores, though more work on rebucketing is needed; storage cavities are running 0.6-0.8 MV instead of design 1 MV. Eve Fri Sep 21 the BRAHMS crossing angle was reduced from 0.9 to 0.45 mrad. 

    SEB beamline momentum has been reduced to 21.5 GeV/c as of Wed Sep 19, with an AGS cycle time of 4.63 seconds and spill length of xx secs. Total AGS extraction intensity is limited to 15 Tp/cycle by Westinghouse invert filter issues. These are being addressed by experts and we should be moving to 20-25 Tp/cycle within the next few days. Servo and spill stability are also being developed as beam is available. 

    The next RHIC experiment maintenance is likely late day Fri Sep 28 for PHENIX photon converter removal; SEB will run at this time and there will be no Linac/Booster/AGS maintenance. 

    Happy Salute The Sun Day, National One-Hit Wonder Day, and National Food Service Workers Day! 
    Happy Birthday to William Faulkner, Mark Rothko, Michael Douglas, Mark Hammill, Heather Locklear, Glenn Gould, and Shostakovitch! 


    Mon Sep 24 2001 21:15: After power dips just after midnight Sat Sep 22, the complex took nearly 24 hours to return to physics production for SEB and RHIC. Four ramps were completed Sun and Mon, leading into the PHENIX photon converter access this morning; the remainder of Mon Sep 24 has been spent in RHIC ramp restoration, abort and injection kicker studies, beta-squeeze, and PLL testing. RHIC 200 MHz storage RF is now routinely on during RHIC stores, though more work on rebucketing is needed; storage cavities are running 0.6-0.8 MV instead of design 1 MV. Eve Fri Sep 21 the BRAHMS crossing angle was reduced from 0.9 to 0.45 mrad. 

    RHIC abort kicker misfirings are being diagnosed as they occur; the event of early Sat Sep 22 was attributed to a misfire of yellow module 3. Since that misfiring, thyrotron voltages have been reduced on all modules, and early this morning the misfiring yellow module 3 thyrotron was replaced; the pulled unit will be evaluated on a test bench. PHOBOS has returned to taking data during RHIC stores as of this weekend. 

    SEB beamline momentum has been reduced to 21.5 GeV/c as of Wed Sep 19, with an AGS cycle time of 4.63 seconds and spill length of xx secs. Total AGS extraction intensity is limited to 15 Tp/cycle by Westinghouse invert filter issues. These are being addressed by experts and we should be moving to 20-25 Tp/cycle within the next few days. Servo and spill stability are also being developed as beam is available. 

    The scheduled maintenance for 0600-0900 PHENIX photon converter installation went well this morning; STAR, RHIC instrumentation, RHIC abort, and RHIC power supply accesses also occurred at that time. There was no SEB running at that time due to the Booster F3 failure; this was repaired later in the day. The next scheduled maintenance is likely early day Fri Sep 28 for PHENIX photon converter removal. 

    Happy Fidelity Day, Festival of the Latest Novelties, and Buy Nothing Day! 
    Happy Birthday to Jim Henson, F. Scott Fitzgerald, Francis Scott Key, Rafael Palmeiro, and Jim McKay! 


    Tue Sep 18 2001 08:45: After a weekend of moderately productive stores and an evening of decent SEB beam early Mon Sep 17, RHIC 200 MHz storage RF was brought to an initial operational status daytime Mon Sep 17; storage cavities at 0.75-0.8 MV instead of design 1 MV. Physicists rebucketed another store that lasted from 22:00 to 02:45, with indications from experiments that vertex distributions were considerably improved. That store was voted down by experiments, but debunched beam quenched the machine and we are currently still in recovery. The objective is to return to RHIC physics before the scheduled 11:00 PHENIX/STAR 3-hour maintenance today, with SEB running (24 GeV/c) throughout the day as feasible. 

    The SEB LESBII separator cable problem has been repaired as of Mon Sep 17. SEB beamline momentum is still at 24 GeV/c; momentum reduction from 24 to 21 GeV/c and spill lengthening is now planned for later today, perhaps during RHIC maintenance. 

    There is currently a scheduled maintenance for PHENIX photon converter installation or field reversal today, Tue Sep 18, from 1100-1400. 

    Shanah Tovah! Happy Kasteilet, National Chocolate Day, and National Play-Doh Day! 
    Happy Birthday to Jonny Quest, Samuel Johnson, Jean Foucault, Bob Dylan, Greta Garbo, Legendre, and Dee Dee Ramone! 


    Fri Sep 14 2001 18:00: After a successful overnight with two RHIC physics stores, the day has been spent in AGS and RHIC maintenance, focusing on repair of the AGS L10 KEK RF cavity, PHENIX muon tracker HV mainframe, Booster F3 magnet, and assorted other repair activities. As of 1600 Au beam has been restored to the W-dump, though RHIC remains off during bi5-sxf sextupole repair. The objective is to return to RHIC and SEB physics (no 200 MHz RF 56-bunch collisions, and 24 GeV/c SEB operation) tonight and through the weekend. 

    There is still a cabling problem with the SEB LESBII separator; a replacement cable is being prepared and will be ready on Mon Sep 17, and repair will not require program downtime. C-line experiments will continue to run this weekend. SEB beamline momentum will stay at 24 GeV/c this weekend, when we will focus on intensity development in the AGS after L10 repair. momentum reduction from 24 to 21 GeV/c and spill lengthening is now planned for Mon Sep 17 as well. 

    RHIC 200 MHz RF development will continue at 0600 on Mon Sep 17, with the intent of semi-operational sequencing of RHIC storage RF by the end of the day. Activites of Thu Sep 13 demonstrated a noise production cut-in in the cavity feedback loops at high voltage (greater than approximately 0.75 MV); a 6-bunch store with cavities at lower voltage demonstrated substantial vertex improvement at all experiments on Thu Sep 13 as well. 

    There is currently a scheduled maintenance for PHENIX photon converter installation on Tue Sep 18 from 1200-1500, after possible RF development in the morning. 

    Happy Formation of the Earth Day, National Anthem Day, and National Cream-Filled Doughnut Day! 
    Happy Birthday to Dante Aligheri, Franz Joseph Haydn, Zarathustra, Allan Bloom, and Bilbo and Frodo Baggins! 


    Thu Sep 13 2001 11:15: After an overnight 8.5 hour physics store following the security shutdown, RHIC 200 MHz RF development is currently ongoing, scheduled until 1200-1300. The objective for this work is to rephase all storage cavities in both rings at storage energy. 

    SEB was dominated by F6 septum problems over most of the night, though these problems were resolved early this morning. After RHIC RF studies, The intent is to return to physics operation as quickly as is possible, including both RHIC collision stores and SEB beam. SEB beamline momentum will stay at 24 GeV/c this evening at the request of E930 so they can complete kaon beam tuning; momentum reduction from 24 to 21 GeV/c and spill lengthening will likely afternoon or evening Fri Sep 14. BRAHMS is currently running with a 0.9 mrad crossing angle; good store ZDC coincidence rates now start between 600 and 800 Hz. 

    There is a scheduled maintenance period on Fri Sep 14 for several repair items: AGS L10 RF cavity gap-shorting relay repair is scheduled to start prep at 0600, and PHENIX HV control mainframe repair is scheduled to start at 0800. This maintenance is expected to complete, with return to RHIC and SEB physics, by mid-afternoon on Friday. Other minor maintenance will also be ongoing, and experiments are being consulted for open work items. 

    Happy Defy Superstition Day, Faulty Day, and Positive Thinking Day! 
    Happy Birthday to Roald Dahl, Milton Hershey, J.B. Priestly, Claudette Colbert, Mel Torme, and Miss Manners! 


    Thu Sep 13 2001 08:40: After an overnight 8.5 hour physics store following the security shutdown, RHIC 200 MHz RF development is currently ongoing, scheduled until 1200-1300. The objective for this work is to rephase all storage cavities in both rings at storage energy. 

    SEB was dominated by F6 septum problems over most of the night, though these problems were resolved early this morning. After RHIC RF studies, The intent is to return to physics operation as quickly as is possible, including both RHIC collision stores and SEB beam. SEB beamline energy reduction from 24 GeV/c to 21 GeV/c and spill lengthening will likely occur this afternoon or evening. BRAHMS is currently running with a 0.9 mrad crossing angle; good store ZDC coincidence rates now start between 600 and 800 Hz. 

    There is a scheduled maintenance period on Fri Sep 14 for several repair items: AGS L10 RF cavity gap-shorting relay repair is scheduled to start prep at 0600, and PHENIX HV control mainframe repair is scheduled to start at 0800. This maintenance is expected to complete, with return to RHIC and SEB physics, by mid-afternoon on Friday. Other minor maintenance will also be ongoing, and experiments are being consulted for open work items. 

    Happy Defy Superstition Day, Faulty Day, and Positive Thinking Day! 
    Happy Birthday to Roald Dahl, Milton Hershey, J.B. Priestly, Claudette Colbert, Mel Torme, and Miss Manners! 


    Wed Sep 12 2001 17:30: We are currently attempting to restore RHIC operations after the 24-hour security shutdown of the C-AD accelerator complex. The intent is to return to physics operation as quickly as is possible, including both RHIC collision stores and SEB beam. SEB beamline energy reduction from 24 GeV/c to 21 GeV/c and spill lengthening will likely occur in the evening Wed Sep 12 or Thu Sep 13. BRAHMS is currently running with a 0.9 mrad crossing angle; good store ZDC coincidence rates now start between 600 and 800 Hz. 

    RHIC 200 MHz development will resume from 0600-1200 Thu Sep 11 -- the objective for this work is to rephase all storage cavities in both rings at storage energy. 

    There is a scheduled maintenance period on Fri Sep 14 for several repair items: AGS L10 RF cavity gap-shorting relay repair is scheduled to start prep at 0600, and PHENIX HV control mainframe repair is scheduled to start at 0800. This maintenance is expected to complete, with return to RHIC and SEB physics, by mid-afternoon on Friday. Other minor maintenance will also be ongoing, and experiments are being consulted for open work items. 

    Happy Defender's Day, Respect for the Aged Day, and National Chocolate Milkshake Day!
    Happy Birthday to Jesse Owens, Barry White, Tim Hardaway, George Jones, Maria Muldaur, and Neil Peart! 


    Tue Sep 11 2001 12:00: In response to the current national situation, we have initiated a 24-hour stand-down of RHIC and AGS physics programs as of 11 AM today. For those who do not have BNL labwide email, I have attached labwide broadcast mail that is relevant to BNL security; note that we should all be wearing ID badges conspicuously, as well as move vehicles, garbage containers, and other potential security hazards away from lab buildings.

    Nationwide air traffic has been grounded, so all users and lab employees should be aware that lack of air travel will impact movement of mail shipments as well as personnel. The long-term impact and schedule of this grounding is unclear at this time.

    There will be a Time Meeting in Snyder Seminar Hall this afternoon at 1:30 as normally scheduled, unless the lab is officially declared closed before then. We will meet at the normal 9 AM meeting tomorrow morning to review the situation, and currently plan to return to physics operations of the complex tomorrow at mid-day, pending further directives from DOE or lab management.

    Stay tuned for further information.


    Mon Sep 10 2001 08:50: After a weekend of productive RHIC stores and downtime atttributed to PASS and QPA faults, we are spending the day in 200 MHz storage cavity development until late afternoon. RHIC production stores and SEB will continue late in the afternoon or early this evening, or earlier if storage cavity development hits an impasse. BRAHMS is currently running with a 0.9 mrad crossing angle; good store ZDC coincidence rates now start between 600 and 800 Hz. 

    Near-term plans continue to focus on RHIC production stores, RHIC 200 MHz storage RF development, and SEB setup/running. Mode switching between RHIC Au and SEB p beam is now routine in 10-20 minutes; SEB beam to E930, E931, and E949 is running at 24 GeV/u, though L10 RF gap-shorting relay work is required for a shift in the AGS before intensities can be substantially increased. This work will be scheduled when RHIC is back to stable operations, and a reduction of SEB momentum to 21 GeV/u is planned for this evening or tomorrow to lengthen the SEB spill and maximize kaon flux. 

    Happy Hot Dog Day, Old-Timer's Day, and National Wienerschnitzel Day!
    Happy Birthday to Arthur Compton, Arnold Palmer, Roger Maris, Charles Kuralt, Amy Irving, Randy Johnson, and Fay Wray! 


    Fri Sep 7 2001 12:30: We are currently working towards beam restoration in RHIC before 200 MHz storage cavity development until late afternoon. The maintenance period Thu Sep 6 went well, and though RHIC was secured by 1800, power supply/quench link and controls problems kept productive beam from the machine throughout the night. BRAHMS is currently running with a 0.9 mrad crossing angle. 

    Near-term plans continue to focus on RHIC production stores, RHIC 200 MHz storage RF development, and SEB setup/running. Mode switching between RHIC Au and SEB p beam is now routine in 10-20 minutes; SEB beam to E930, E931, and E949 is running at 24 GeV/u, though L10 RF gap-shorting relay work is required for a shift in the AGS before intensities can be substantially increased. This work will be scheduled when RHIC is back to stable operations, and a reduction of SEB momentum to 21 GeV/u is planned for Mon Sep 10 or Tue Sep 11 to lengthen the spill for E930 in the D line. 

    Happy Granddad's Day, Neither Snow Nor Rain Day, Kielbasa Festival, and Festival of Durga (Goddess of Energy)! 
    Happy Birthday to Grandma Moses, Chrissy Hynde, Sonny Rollins, Buddy Holly, Richard Roundtree, Daniel Ken Inouye, and James Van Allen! 


    Wed Aug 29 2001 16:45: We are currently recovering from the scheduled maintenance for the day, that included Westinghouse motor generator cleaning and BRAHMS high voltage repair. RHIC magnets have been cycled, all maintenance activities are complete, and RHIC areas are being swept while beam is restored to the Booster and AGS. BRAHMS is currently running with a 0.9 mrad crossing angle. 

    Near-term plans focus on RHIC production stores, RHIC 200 MHz storage RF development, and SEB setup. Earlier this morning operations and experts performed a mode switch to h=6 SEB and achieved proton extraction to switchyard though bug fixes to AGS main magnet software and more extraction and switchyard setup is necessary before SEB beam is available for experiments. This an operational SEB mode switching are operational priorities before the long Labor Day weekend. 

    Happy According To Hoyle Day, More Herbs Less Salt Day, and National Whisky Sour Day! Happy Birthday to John Locke, Oliver Wendell Holmes, Jack Butler Yeats, Ingrid Bergman, and Richard Gere! 


    Fri Aug 24 2001 15:05: We are currently working towards restoration of RHIC physics ramps after yesterday's maintenance period. As of 14:40 we have a restored a good 56-bunch ramp that produced peak ZDC rates of 400 Hz in detectors. The near objectives are to produce physics ramps, punctuated with 6-bunch ramps to continue 200 MHz storage RF setup. The blue main power supply offset of yesterday and last night has been eliminated; the y10-q89 supply was replaced twice last evening, and ramps this morning were compromised by beam loss due to trips of yo12-tq5. 

    The scheduled maintenance was successful during the day yesterday; STAR completed their planned EMCal work, PHENIX installed muID shielding, and BRAHMS restored high voltage to one of their drift chambers. During that maintenance, the 2 o'clock DX magnets were ramped to full field without problems; we will likely reduce the crossing angle at BRAHMS from 1.8 mrad to 0.9-1.0 mrad tonight or tomorrow to improve their diamond length. The machine will continue to operate at the reduced 4.73 K ring temperature, down from 4.89 to improve DX quench margin. 

    SEB setup successfully injected and accelerated h=6 proton beam in the AGS, with peak flattop intensities of a 2-3 Tp. p/Au switching was performed twice, with the second p->Au switch taking only 15-20 minutes, with few manual tuning requirements. Upon consistent production of 6+-hour stores in RHIC, setup will continue with extraction and switchyard tuning; this is anticipated for early next week, possibly Sun Aug 26 or Mon Aug 27. BLIP is back online after a target failure on Wed Aug 22. 

    Happy Schaferlauf, Bartholomew Fair, and National Peach Pie Day! Happy Birthday to Steve Gutenberg, Jorge Luis Borges, Marlee Matalin and Cal Ripkin Jr! 


    Thu Aug 23 2001 08:35: We are currently in scheduled maintenance through the day, 0800-1800. Work scheduled in this period includes RHIC power supply maintenance, RHIC snake power supply work, and RHIC experimental work (including STAR EMC and other work, BRAHMS and PHENIX work). During this period, we will also be working on mode-switchable SEB setup, with the end-maintenance objective of AGS acceleration and extraction setup with 15-minute mode switching. 

    Physics ramps were restored as of 2200 last evening, though the first store was voted down after a few hours due to low ZDC rates. The second ramp at 0140 lasted 6.5 hours until it was dumped just after 0800 this morning; this is significantly longer than any ramp has survived without interlocks over the past week. Maximal ZDC rates were only 130-150 Hz at start of store, so we will return to ramp and physics tuning after the maintenance period later tonight. Happy Festival of Fire, Permanent Press Day, and National Spongecake Day! Happy Birthday to Mark Russell, Barbara Eden, Edgar Lee Masters, Keith Moon, River Phoenix, and Gene Kelly! 


    Wed Aug 22 2001 11:15: Today's maintenance/repair on the RHIC main power supplies has been shortened, with an expected completion time of 1500. There have been several successful no-beam ramps this morning, and power supply personnel are diagnosing and evaluating the health of the main power supplies and blue quench link interrupts before returning the system to operations. There will be no proton setup activities today; instead, operations will start sweeping areas at noon and have Au beam ready in the injectors for a return to RHIC injection and ramping around 3 PM. 

    There is still a scheduled maintenance period during the day tomorrow, Thu Aug 23 0800-1800 as originally scheduled. Work scheduled in this period includes RHIC power supply maintenance, RHIC snake power supply work, and RHIC experimental work (including STAR EMC and other work, BRAHMS broken-wire drift chamber pull, and PHENIX work). During this period, we will also be working on mode-switchable SEB setup, with the end-maintennce objective of AGS acceleration and extraction setup with 15-minute mode switching. 

    Happy Be An Angel Day, Americas Cup Day, and National Pecan Torte Day! Happy Birthday to Ray Bradbury, Dorothy Parker, Claude Debussy, John Lee Hooker, Honor Blackman, and Carl Yaztremski! 


    Wed Aug 22 2001 10:45: Today is a maintenance/repair day following two days of attempts to recover RHIC operations after power dips and network problems. The primary problems are currently in the RHIC main power supply hardware; George Ganetis and experts will be investigating through the day. We are evaluating the possibility of starting SEB setup late this evening instead of daytime tomorrow. 

    There is still a scheduled maintenance period during the day tomorrow, Thu Aug 23 0800-1800, although this maintenance may be shortened if substantial work can be accomplished during today's RHIC power supply repairs. Work scheduled in this period includes RHIC power supply maintenance, RHIC snake power supply work, and RHIC experimental work (including STAR EMC and other work, BRAHMS broken-wire drift chamber pull, and PHENIX work). During this period, we will also be working on mode-switchable SEB setup, with the end-maintennce objective of AGS acceleration and extraction setup with 15-minute mode switching. 

    Happy Be An Angel Day, Americas Cup Day, and National Pecan Torte Day! Happy Birthday to Ray Bradbury, Dorothy Parker, Claude Debussy, John Lee Hooker, Honor Blackman, and Carl Yaztremski! 


    Fri Aug 3 2001 17:50 Todd will be away from the lab Sat Aug 4-Sat Aug 18. Yousef Makdisi has kindly agreed to bear the Scheduling Physicist pager in this period and run the Aug 7 and 14 Time Meetings. Dejan Trbojevic has also kindly agreed to coordinate activities related to RHIC program development and maintenance. 

    Earlier today there was a significant failure in the Siemens building. GE personnel are on their way, and we are mobilizing personnel to switch the AGS ring back to the Westinghouse supply as soon as possible. If all goes well, we expect to return to Au beam in RHIC sometime late tonight or during the day Sat Aug 4. Damage from the Siemens failure needs to be assessed to evaluate the impact to the AGS SEB program, and meetings are planned for Mon Aug 6 to discuss alternatives, though full restoration of the RHIC program takes the highest priority. 

    Over the past day, we have had several successful 56-bunch ramps and 100 GeV/u collisions, with ZDC coincidence rates above 100 Hz in some experiments and modest (1-2x10^8 Au ions) beam intensities. Several hours were spent during the day yesterday on intrabeam scattering and collimation studies in both rings. 

    Today and tonight will be spent moving to the Westinghouse motor generator and restoring beam to the AGS. Depending on the success of beam restoration, the remainder of the weekend will be spent in RHIC beam restoration and 56-bunch luminosity production. Long-term plans concentrate on 200 MHz storage RF development during the days and luminosity production ramps over evenings and nights. Proton SEB development plans will be reviewed and discussed on Mon Aug 6. 

    Linac will be delivering beam to BLIP through the weekend, but will still be down Mon Aug 6 and Tue Aug 7 for SEB preparation maintenance. 

    Happy Feast of Caligo, National Watermelon Day, and Anniversary of First Golf on the Moon! Happy Birthday to Martin Sheen, Tony Bennett, Ann Klein, Ernie Pyle, and Clifford D. Simak! 


    Fri Aug 3 2001 10:35 Todd will be away from the lab Sat Aug 4-Sat Aug 18. Yousef Makdisi has kindly agreed to bear the Scheduling Physicist pager in this period and run the Aug 7 and 14 Time Meetings. Dejan Trbojevic has also kindly agreed to coordinate activities related to RHIC program development and maintenance. 

    Over the past day, we have had several successful 56-bunch ramps and 100 GeV/u collisions, with ZDC coincidence rates above 100 Hz in some experiments and modest (1-2x10^8 Au ions) beam intensities. Several hours were spent during the day yesterday on intrabeam scattering and collimation studies in both rings. 

    Today from 08:00 to 17:00 will be spent developing 200 MHz storage RF (6 bunches, some ramp tuning), and Saturday from 08:00 to 12:00 will be spent working on orbit correction and ramp loss correction near transition with 6-bunch acceleration ramps. The remainder of the weekend will be spent in 56-bunch luminosity production. Long-term plans concentrate on 200 MHz storage RF development during the days and luminosity production ramps over evenings and nights, with a return to proton SEB development on Wed Aug 8. 

    Linac will be delivering beam to BLIP through the weekend, but will be down Mon Aug 6 and Tue Aug 7 for maintenance. The return to proton SEB development on Wed Aug 8 will focus on AGS mode switching, including ramping and extraction; this activity is dependent on hiding an F10 short repair behind a RHIC store before that time. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 10, depending on how RHIC development proceeds. 

    Happy Feast of Caligo, National Watermelon Day, and Anniversary of First Golf on the Moon! Happy Birthday to Martin Sheen, Tony Bennett, Ann Klein, Ernie Pyle, and Clifford D. Simak! 


    Wed Aug 1 2001 15:15 We are currently in power supply, experimental maintenance, and proton mode switching startup until 1700. Power supply maintenance includes code changes to the quench protection system for better quench diagnosis, and some IR and gammaT hardware repair. Experimental maintenance is mostly for PHENIX, for drift chamber bubbler piping installation and analysis/recovery from their cooling water crash overnight. Proton mode switching startup will restore protons to the Booster and BTA, before working on beam capture and acceleration (including RF mode switching) in the AGS. 

    Over the past 24 hours, we have delivered events to experiments approximately 70% of the time! The yellow orbit was improved and beam steering at all experiments were performed during the day shift yesterday, and 56 bunches were injected (but not accelerated) into each ring in the evening. Our immediate beam plans will focus on maintenance recovery, gammaT and ramp tuning for transmission, and tests of 56-bunch injection and acceleration. We intend to move to routine 56-bunch stores overnight during production within the next few days, and day development activities will mostly concentrate on 6-bunch ramping and 200 MHz RF commissioning. Other Machine Physics studies are currently scheduled from 1000 to 1400 Thu Aug 2. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. status. 

    Happy National Night Out, Laughter Day, and Rounds Resounding Day! Happy Birthday to Giancarlo Giannini, Herman Melville, Robert Cray, Dom DeLuise, Jerry Garcia, and Juliet Capulet! 


    Sun Jul 29 2001 11:15 We are currently in the middle of a series of 6x6 event-production stores, being used by experiments for system timing and initial data acquisition. These stores started late Sat Jul 28, after recovery from RF and power supply issues. We expect to have another set of stores throughout the evening, punctuated by first attempts to ramp 56 bunches in both rings; if successful, these ramps may be cogged to investigate ZDC rates, but they will not be kept at storage for luminosity production at this time. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. The MP6 to MP7 switchover is scheduled for AM Mon Jul 30 and should take approximately 2 hours; specific timing will be determined by RHIC status. 

    Happy First Assembly Day, Dragon Day, and Festival of the Polymorphously Perverse! Happy Birthday to Dag Hammarskjold, Rasputin, Peter Jennings, Wil Wheaton, and Ken Burns! 


    Fri Jul 27 2001 13:15 We continue repair work and checkout of blue main dipole power supply issues that have kept us off overnight. After overnight work, line crews returned this morning, and main power supply checkout has continued with a successful ramp up and down from top energy accomplished near noon today. We are planning to recover operations late afternoon and into the evening with the same focus as beam recovery last evening: restoration of Au beam, RHIC ramping and collisions for all experiments

    From yesterday, RHIC RF work included accelerating cavity driver amplifier replacement (2 hours); the afternoon was spent conditioning the two accelerating cavities that require conditioning. RHIC power supply work included y8-q7 diagnosis/repair, bi8-qf3 repair, yi3-sxd repair, QPA KLOC tightening and maintenance, main power supply development, and other miscellaneous items. 

    Preparations for HEP proton operation and mode switching in the linac, Booster, and AGS included AGS tunnel access for proton instrumentation setup. Mode switching made it to the point of spiraling beam in the AGS; further progress depends on testing of new mode-switchable Booster/AGS synchro equipment. Recovery of Au beam in Booster and AGS was straightforward on Thu afternoon. 

    When several consistent ramps have occurred and experiments agree, we will move to 56 bunches to evaluate ramps with higher intensity. This will demand close contact with experiments, and with the cryo control room in the event of a ramping or high-energy quench link interlock; real magnet quenches are possible with this much beam in RHIC. AGS/RHIC synchro and phase detector issues related to RHIC fills have been resolved. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. 

    Happy Gilroy Garlic Festival, Take Your Plants For A Walk Day, and National Blunt Object Day! Happy Birthday to Keenan Wynn, Peggy Fleming, Leo Durocher, Confucius, and Bugs Bunny! 


    Fri Jul 27 2001 08:35 Although power supply maintenance was scheduled to end last evening 2200-2300, the overnight period was spent in maintenance for a blue main dipole power fault, with line crews and Carl Schultheiss working all night. We are planning to recover operations during the day today, with the same focus as beam recovery last evening: restoration of Au beam, RHIC ramping and collisions for all experiments

    From yesterday, RHIC RF work included accelerating cavity driver amplifier replacement (2 hours); the afternoon was spent conditioning the two accelerating cavities that require conditioning. RHIC power supply work included y8-q7 diagnosis/repair, bi8-qf3 repair, yi3-sxd repair, QPA KLOC tightening and maintenance, main power supply development, and other miscellaneous items. 

    Preparations for HEP proton operation and mode switching in the linac, Booster, and AGS included AGS tunnel access for proton instrumentation setup. Mode switching made it to the point of spiraling beam in the AGS; further progress depends on testing of new mode-switchable Booster/AGS synchro equipment. Recovery of Au beam in Booster and AGS was straightforward on Thu afternoon. 

    When several consistent ramps have occurred and experiments agree, we will move to 56 bunches to evaluate ramps with higher intensity. This will demand close contact with experiments, and with the cryo control room in the event of a ramping or high-energy quench link interlock; real magnet quenches are possible with this much beam in RHIC. AGS/RHIC synchro and phase detector issues related to RHIC fills have been resolved. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. 

    Happy Gilroy Garlic Festival, Take Your Plants For A Walk Day, and National Blunt Object Day! Happy Birthday to Keenan Wynn, Peggy Fleming, Leo Durocher, Confucius, and Bugs Bunny! 


    Thu Jul 26 2001 10:45 The schedule for today concentrates on preparations for HEP proton operations and mode switching, RHIC RF repair/conditioning, and RHIC power supply repair/maintenance. This period is expected to last from 0830 to approximately 1900. Upon beam return, the evening and overnight will focus on restoration of Au beam, RHIC ramping and collisions for all experiments

    RHIC RF work includes accelerating cavity driver amplifier replacement (2 hours); the afternoon will be spent conditioning the two accelerating cavities that require conditioning. RHIC power supply work includes y8-q7 diagnosis/repair, bi8-qf3 repair, yi3-sxd repair, QPA KLOC tightening and maintenance, main power supply development, and other miscellaneous items. Power supply and ramping recovery will be highly weather-dependent. 

    Preparations for HEP proton operation and mode switching in the linac, Booster, and AGS include AGS tunnel access for proton instrumentation setup. Dry mode switching activities will be coordinated with this setup; if weather and beam setup permit, some proton beam delivery to Booster and AGS will be attempted later this afternoon.

    When several consistent ramps have occurred and experiments agree, we will move to 56 bunches to evaluate ramps with higher intensity. This will demand close contact with experiments, and with the cryo control room in the event of a ramping or high-energy quench link interlock; real magnet quenches are possible with this much beam in RHIC. AGS/RHIC synchro and phase detector issues related to RHIC fills have been resolved. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. 

    Happy All Or Nothing Day, Curacaco Day, and National Coffee Milkshake Day! Happy Birthday to Carl Jung, Stanley Kubrick, Blake Edwards, Mick Jagger, George Clinton, Donald Vorhees, Dorothy Hamill, and Bert from Sesame Street! 


    Fri Jul 20 2001 10:50 We are currently in a brief access for STAR FTPC pump analysis as well as yellow RF cavity tuning, based on problems with the yellow 3.2 acceleration cavity overnight. After this access, we will return to RHIC injection to study new synchro/cogging software and verify yellow RF cavity stability before returning to ramping. 100 GeV/u ramping is expected for the remainder of the day and into the evening, with efforts focusing on ramp tuning and measurements (including chromaticity and coupling). The objective is to have stable reproducible ramping for the weekend. 

    When several consistent ramps have occurred and experiments agree, we will move to 56 bunches to evaluate ramps with higher intensity. This will demand close contact with experiments, and with the cryo control room in the event of a ramping or high-energy quench link interlock; real magnet quenches are possible with this much beam in RHIC. 

    Yesterday's maintenance period allowed the power supply group to diagnose and fix the main yellow quad DCCT problem, QPA PLC code, and problems with quench protection trips during transition from flat-bottom to ramping. Regulation issues for many power supplies were corrected, and gammaT power supplies were repaired. Further quench protection tuning will be desireable early next week. The RF RHIC/AGS synchro work was not successful for four bunch extraction; if/when we ramp 56 bunches, we will fill at the rate of 3 AGS bunches per cycle. 

    Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is now scheduled for c. Aug 8, depending on how RHIC startup proceeds. 

    Happy Ugly Truck Contest Day, National Lollipop Day, and Chess Day, and Happy Birthday to Edmund Hillary, Diana Rigg, Carlos Santana, Nelson Doubleday, Theda Bara, and Donna Dixon! 


    Wed Jul 18 2001 12:15 At 23:30 Tue Jul 17, we had a successful 100 GeV/u ramp that achieved confirmed acquired collisions at all four RHIC experiments. This store lasted 1.5 hours during which steering and timing was performed at all four experiments; the store was manually dumped at 01:00, but quench link interrupts were pulled by a power dip just as the main magnets started to ramp down. We are currently working on RF issues related to 56 bunch injection and automatic open-loop cogging at injection, before returning to ramps and further RF studies this afternoon. The evening and overnight will continue 100 GeV/u ramping, with focus on instrumentation and experimental setup and timing. Both rings are currently tuned for 100 GeV/u ramps, slow factor 2 up and down

    Tomorrow during the day, a shift will be taken for power supply repair work (including QPA software improvements, main power supply transition improvements, 720 Hz transient analysis). During this period, the Yellow 3.1 RF cavity will be reconditioned and assorted known power supply failures will be addressed. 

    The polarized proton source has been on this weekend, setting up and studying beam to the 200 MeV HEBT polarimeter. Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 and NP/E930/E931 mode switching for AGS SEB is still scheduled for Aug 1, though this will likely shift as RHIC startup proceeds. 

    Happy National Caviar Day, Railroad Day, and Chrysanthemum Day, and Happy Birthday to Nelson Mandela, John Glenn, Hunter S. Thompson, Robert Hooke, Horatio Alger, and Joe Torre! 


    Tue Jul 17 2001 11:40 Through the course of the wee hours today, we have had two successful ramps of beam to 100 GeV/u; one ended quickly with a quench link interlock, the other stayed up for approximately 25 minutes before the yellow main quadrupole regulation circuits unlocked and beam was lost. The only ZDC coincidences observed during the latter ramp were seen at BRAHMS, with rates of approximately 5 Hz, though several dipole correctors had tripped off during the ramp. Both rings are currently tuned for 100 GeV/u ramps, slow factor 2 up and down. We are currently in maintenance for the remainder of the day, working on power supply and RF systems. 

    It is important to note that the beam survival from 65 GeV/u to 100 GeV/u looks extremely clean and reproducible. No tuning was required between successful ramps at these different energies. 

    Several maintenance and repair activities occurred over the weekend in conjunction with tuneup, concentrating on yellow abort kicker issues (done), yellow RF 3.1 cavity trips (ongoing), gammaT power supply level tuning (done), fix of ramping software glitches (done), and yellow main dipole power supply repair (done). Ramps and collisions at 65 GeV/u were restored early morning Mon Jul 16, with indications that further tuning of blue gammaT jump supplies is necessary. Because ramp reproducibility remains an issue, there has been no aggressive push towards study of high-intensity ramps at this time. 

    The polarized proton source has been on this weekend, setting up and studying beam to the 200 MeV HEBT polarimeter. Linac/BLIP performed initial startup Mon Jul 16, and BLIP is currently running. Start of HEP/E949 mode switching for AGS SEB is still scheduled for Aug 1.

    Happy Dodge City Day, Wrong Way Day, Crank Call Day, and Feast of the Clockless Nowever, and Happy Birthday to Art Linkletter, James Cagney, Phyllis Diller, Darryl Lamonica, and Peter Schickele! 


    Mon Jul 16 2001 0945: Power supply personnel continue to work on 100 GeV/u ramp tuneup today, concentrating on the Yellow ring. On Sunday the blue ring was tuned to slow factor 2 up and (likely) down, though housekeeping power supply failures, occasional quench link events, and gas-cooled lead flow tuning made progress slow. The first 100 GeV/u ramp tests with beam will be Eve Mon Jul 16, definitely with the blue ring and possibly with both rings if feasible. 

    Several maintenance and repair activities occurred over the weekend in conjunction with tuneup, concentrating on yellow abort kicker issues (done), yellow RF 3.1 cavity trips (ongoing), gammaT power supply level tuning (done), fix of ramping software glitches (done), and yellow main dipole power supply repair (done). Ramps and collisions at 65 GeV/u were restored early morning Mon Jul 16, with indications that further tuning of blue gammaT jump supplies is necessary. Because ramp reproducibility remains an issue, there has been no aggressive push towards study of high-intensity ramps at this time. 

    The polarized proton source has been on this weekend, setting up and studying beam to the 200 MeV HEBT polarimeter. Linac/BLIP are still scheduled for initial startup Mon Jul 16 and full operation on Tue Jul 17. Start of HEP/E949 mode switching for AGS SEB is still scheduled for Aug 1. 

    Happy Atomic Bom Day, International Juggling Day, and Festival of Convivial Tools, and Happy Birthday to Mary Baker Eddy, Ruben Blades, Phoebe Cates, Stewart Copeland, Orville Redenbacher, and Shoeless Joe Jackson! 


    Sun Jul 15 2001 1820: Power supply personnel have been working on 100 Gev/u ramp tuneup in both RHIC rings since early Saturday. Substantial progress is being made, though slow due to housekeeping power supply failures, occasional quench link events, and gas cooled lead flow tuning. We anticipate that this activity will continue into Mon Jul 16, with first 100 GeV/u ramp tests with beam possible as early as Mon eve. 

    Several maintenance and repair activities have been ongoing in conjunction with tuneup, concentrating on yellow abort kicker issues (done), yellow RF 3.1 cavity trips (ongoing), gammaT power supply level tuning (done), fix of ramping software glitches (done), and yellow main dipole power supply repair (done). Attempts to ramp beams to 65 GeV/u early Sun Jul 15 were compromised by yellow main dipole problems and gammaT tuning issues. These will be readdressed upon return to ramping overnight tonight. Because ramp reproducibility remains an issue, there has been no aggressive push towards study of high-intensity ramps at this time. 

    The polarized proton source has been on this weekend, setting up and studying beam to the 200 MeV HEBT polarimeter. Linac/BLIP are still scheduled for initial startup Mon Jul 16 and full operation on Tue Jul 17. Start of HEP/E949 mode switching for AGS SEB is still scheduled for Aug 1. 

    Happy St Bonaventure's day, Confuflux, and National Ice Cream Day, and Happy Birthday to Harrison Birtwistle, Julian Bream, Clement Moore, Thomas Bullfinch, and Richard Armour!
    Today in 1876, George Washington Bradley pitched the first no-hitter in baseball by leading St. Louis to a 2-0 win over Hartford. 


    Thu Jul 12 2001 1210: During the day today, we are concentrating on injection, synchro, decoupling, and instrumentation timing issues; after lunch Carl Schultheiss will require a few hours to instrument the yellow main supplies to attempt to catch and diagnose problems related to recent quench link events. The majority of the day Wed Jul 11 was spent recovering from a storm shutdown as well as repairing a shorted AGS fan house feeder cable. Overnight there were several reproducible stores with approximately 65% ramp transmission in both rings, using shortened gammaT ramps of 5 secs instead of the previously used 10 sec ramps. 

    Beam activities overnight and through the day on Fri Jul 13 will concentrate on ramp tuning with high-intensity beams, learning about machine performance and possible intensity-related instabilities during the acceleration ramps. Some limited testing of development ramps will also be performed when time is available. 

    The next major activity here will be one to two days of tuning on Sat Jul 14 and Fri Jul 15 to develop robust 100 GeV/u ramps for beam. Due to delays in software development and missing perssonel, this activity has how been delayed several days. During this period when beam is available, we will continue ramping with beam to 65 GeV/u or 100 GeV/u as available. 

    Happy Visitation Day, Video Games Day, and Anniversary of Thor Heyerdahl's trip! Happy birthday to Henry David Thoreau, George Eastman, Buckminster Fuller, Pablo Neruda, Andrew Wyeth, and Van Cliburn! 


    Thu Jul 12 2001 0840: The past several days have been spent working on continued 65 GeV/u ramp tuning, including IR steering, ZDC timing, and collisions at PHENIX, STAR, and PHOBOS over the past two nights. The majority of the day Wed Jul 11 was spent recovering from a storm shutdown as well as repairing a shorted AGS fan house feeder cable. Overnight there were several reproducible stores with approximately 65% ramp transmission in both rings, using shortened gammaT ramps of 5 secs instead of the previously used 10 sec ramps. 

    The next major activity here will be one to two days of tuning on Thu Jul 12 and Fri Jul 13 to develop robust 100 GeV/u ramps for beam. Due to delays in software development, this activity is not expected to start until late in the day Thursday. 

    Happy Visitation Day, Video Games Day, and Anniversary of Thor Heyerdahl's trip! Happy birthday to Henry David Thoreau, George Eastman, Buckminster Fuller, Pablo Neruda, Andrew Wyeth, and Van Cliburn! 


    Mon Jul 9 2001 0845: We have been ramping both beams reproducibly to gamma=70 for the majority of the weekend, concentrating on ramp tuning, synchro/cog, instrumentation timing, and gamma=70 optics. There has been very little steering done in the IRs to this point. Even without this, PHOBOS have reported a handful of confirmed collisions and all experimental ZDCs are showing some coincidences as experimental systems are timed in. We are still suffering occasional quench link trips as well as RF system trips, both up the ramp and at gamma=70. 

    Perhaps as early as late today, there will be a 3-5 hour shutdown to give George time for his final gamma=100 ramp tuning measurements; we anticipate ramps to gamma=100 two to three days after this data is acquired. To minimize impact, we are also coordinating this work with HEP proton run preparation work, including linac vacuum checkout, through this morning's meetings. 

    Happy Fashion Day, Call of the Horizon Day, and Festival of Grand Unified Theories, and Happy Birthday to Tom Hanks, Richard Roundtree, Kelly McGillis, Franz Boaz, and Nikola Tesla! 


    Fri Jul 6 2001 1020: After this morning's 9 AM meeting, we are now giving power supply personnel another shift (1000-1800 Day Fri Jul 6) to repair a lead flow problem and reacquire 100 GeV ramp data; the data taken on Tue Jul 3 was compromised by Booster noise. With successful data today, we anticipate start of 100 GeV ramping early next week, perhaps Mon Jul 9 or Tue Jul 10. Other maintenance being performed at this time includes PHENIX He bag replacement, finishing work on Blue gammaT supplies, polarity corrections of Yellow gammaT supplies, and repair of a few known bad 50 A correctors. We will likely return to beam activities between 1800 and 2000 today. 

    In the meantime, crews continue to aggressively work to accelerate beams in both rings since late eve Sun Jul 1. This activity mainly focuses on tunes, chromaticities, and radial steering through the acceleration cycle, with particular focus on orbit/tune problems in the yellow ring just before transition, even with transition crossing supplies off. Beam is being routinely accelerated to gamma=70 in the blue ring; it is being routinely lost at transition energy in the yellow ring. 

    Happy National Fried Chicken Day, Old Albums Are Frisbees Day, and Nothing Day, and Happy Birthday to Beatrix Potter, John Byrne, Gene Chandler, Janet Leigh, and the Dalai Lama! 


    Tue Jul 3 2001 1130: After a long storm-filled weekend, crews have been aggressively working to accelerate beams in both rings since late eve Sun Jul 1. This activity mainly focuses on tunes, chromaticities, and radial steering through the acceleration cycle. Beam has been repeatedly accelerated to gamma=70 in the blue ring, and was accelerated through transition energy early this morning. Local and global decoupling of the yellow ring on Mon Jul 2 was quite successful. 

    We are now giving power supply personnel a shift (Day Tue Jul 3) to train DX quenches for 100 GeV/u ramps; other maintenance being performed at this time includes PHENIX He bag replacement, RHIC tunemeter repair, radial loop analysis, and continuing work on Yellow gammaT power supplies. We will likely return to beam activities between 1600 and 1800 today, though this may change depending on speed of quench training progress. If the DX training is successful, we will continue ramping activities to gamma=70, and proceed to design energies later in the week. Beam activities are on Dejan Trbojevic's Shift Update page. 

    Happy Stay Out Of The Sun Day, Quiz Day, and Disobedience Day, and Happy Birthday to Samuel de Champlain, Betty Buckley, George M. Cohan, Tom Stoppard, and Thomas Mapother (aka Tom Cruise)!

    A belated Happy 95th birthday to Hans Bethe! 


    Fri Jun 29 2001 1715: As of earlier today, beam has been circulating in both blue and yellow rings at injection. We have made good progress in instrumentation timing in the yellow ring, and achieved decent lifetime with RF-captured single bunches. Remaining work in the yellow ring at injection includes instrumentation timing, orbit improvement, decoupling, and optics analysis. 

    Activities tonight include quench protection tuning for fast yellow ramps and checkout of the tenth yellow gammaT power supply in the tunnel. We will return to blue beam at approximately 2000, when we will attempt further blue acceleration ramps to evaluate issues of radial steering around transition. Overnight and through the weekend, we will focus on yellow ring injection and instrumentation, and ramping of both rings to gamma=70 to establish collisions. Beam activities are on Dejan Trbojevic's Shift Update page. 

    DX Training has been deferred to the week of July 2, as our current program priority is to establish a beachhead demonstration of collisions at gamma=70. Gamma=70 collisions may occur at any time over the weekend; we expect to spend a limited time (a shift or less) performing timing and hardware checks at this point, then start DX training for design energy operation. Stay tuned! 

    Happy Flower and Camera Day, Peter and Paul Day, and Sacrament of the Silicon Host, And Happy Birthday to Antoine de Saint-Exupery, Slim Pickens, Nelson Eddy, Fred Grandy, Pedro Guerrero, and Ruth Warric! 


    Thu Jun 28 2001 2120: MCR are returning beam to the AGS after a rate-of-rise fire alarm in the AGS stopped beam development at 1320 this afternoon. The source of the difficult-to-find alarm was a