Linac Status Infomation for MCR and CAS

Version June 16 2008, 0900 hrs


06-02-08 - 12-29-08

The Linac is off.All sytems are off except tower pump and chiller.There is no vacuum systems on in Lebt at this time.

Collider Accelerator Support (CAS) Checks:

1) Always check Linac High Vac ion pump power supplies and Lebt Vac systems after a storm or once a day.All Linac tanks are under vacuum and all ion pumps for those tanks are on.Hebt pumps A,A1,A2 & Blip B,C,D&E should be on.

3) Linac nitrogen system on line with bladder system and outside dewar.Compressor broke.The nitrogen alarm works from the pump room.Inform Brian on any change.